| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.40
| 0.20 | 0.20 | $5,000.00 | $1,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.40
| 0.20 | 0.20 | $5,000.00 | $1,000.00 |
| 6 | OFFICE FACILITIES | 5.00 | MTH |
1.25
| 0.25 | 1.00 | $7,500.00 | $7,500.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.95
| 0.50 | 0.45 | $145,000.00 | $65,250.00 |
| 8 | CLEARING AND GRUBBING | 1.00 | LS |
0.60
| 0.50 | 0.10 | $10,000.00 | $1,000.00 |
| 9 | CROWN REDUCTION W/ROOT PRUNING, TREE (13" - 24" DIAMETER) | 10.00 | EA |
1.00
| 0.00 | 1.00 | $800.00 | $800.00 |
| 10 | REMOVE EXISTING CHAIN LINK FENCE | 4,200.00 | LF |
1,000.00
| 0.00 | 1,000.00 | $6.50 | $6,500.00 |
| 13 | TRAFFIC CONTROL | 1.00 | LS |
0.40
| 0.20 | 0.20 | $25,000.00 | $5,000.00 |
| 14 | LANDSCAPING | 1.00 | LS |
0.20
| 0.00 | 0.20 | $165,000.00 | $33,000.00 |
| 15 | IRRIGATION SYSTEM | 1.00 | LS |
0.60
| 0.50 | 0.10 | $318,500.00 | $31,850.00 |
| 17 | TREE PROTECTION FENCING | 1.00 | LS |
0.70
| 0.60 | 0.10 | $21,000.00 | $2,100.00 |
| 19 | TUBULAR STEEL FENCE, 8' HIGH | 3,734.00 | LF |
500.00
| 0.00 | 500.00 | $270.00 | $135,000.00 |
| S-1 | EXTEND NTP PART 1 DURATION | | WD |
14.00
| 0.00 | 14.00 | $0.00 | $0.00 |
| S-2 | CITY OF LA PERMIT FEES | | T&M |
9,726.30
| 0.00 | 9,726.30 | $1.00 | $9,726.30 |
|