| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | OFFICE FACILITIES | 6.00 | MO |
3.00
| 2.00 | 1.00 | $5,000.00 | $5,000.00 |
| 3 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.45
| 0.30 | 0.15 | $10,000.00 | $1,500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.45
| 0.30 | 0.15 | $25,000.00 | $3,750.00 |
| 5 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MO |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 26 | ELECTRICAL WORK | 1.00 | LS |
0.339
| 0.125 | 0.214 | $350,000.00 | $74,900.00 |
| 30 | UNCLASSIFIED EXCAVATION LANDSCAPE | 1,207.00 | CY |
1,126.00
| 977.00 | 149.00 | $100.00 | $14,900.00 |
| 40 | IRRIGATION | 1.00 | LS |
0.152
| 0.112 | 0.04 | $80,000.00 | $3,200.00 |