Progress Payment 11
Project Name: Altadena - Altadena Dr and Washington Blvd Roadway Improvement
Contractor: Sully-Miller Contracting Company
135 South State College Boulevard, Suite 400
Brea, CA 92821
Project ID: RMD2504001
Federal Number(s): None
Original Contract: $5,543,838.70
Awarded: 1/22/2024
Period Ending: 4/6/2025
Board Accepted: 11/18/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)11.00MTH 11.00 10.001.00$500.00$500.00
9OFFICE FACILITIES12.00MTH 10.00 8.002.00$7,500.00$15,000.00
62INSTALL 6' DIAMETER CIRCULAR LOOPS2.00EA 2.00 0.002.00$2,000.00$4,000.00
674-CAMERA VIDEO DETECTION SYSTEM (COMPLETE)2.00EA 2.00 1.500.50$60,000.00$30,000.00
90SWITCH PACK9.00EA 9.00 7.002.00$50.00$100.00
S-27CONTRACT TIME EXTENSION (5 NON-WD) - EATON FIRE NWD 5.00 0.005.00$0.00$0.00
S-27ACONTRACT TIME EXTENSION (4 NON-WD) - EATON FIRE NWD 4.00 0.004.00$0.00$0.00
S-31RUBBER WALK DEEPENED EDGE LS 1.00 0.001.00$27,327.56$27,327.56
S-33EATON FIRE TC PICK UP LS 1.00 0.001.00$9,197.00$9,197.00
S-34ALTADENA DR STORM RUNOFF CLEAN UP LS 1.00 0.001.00$1,781.00$1,781.00
S-35SURVEY MONUMENT INVESTIGATION LS 1.00 0.001.00$2,901.00$2,901.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGETED WORKER HIRING PROGRAMSTIP 3,011.37 2,461.61549.76$1.00 $549.76

FINANCIAL SUMMARY

  Total Previous Current
Earned $6,032,494.94 $5,941,688.38 $90,806.56
Retained* $301,624.79 $297,084.46 $4,540.33
Deducted $3,011.37 $2,461.61 $549.76
Due $5,727,858.78 $5,642,142.31 $85,716.47