Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: Cogswell Dam Inlet - Outlet Works Rehabilitation Project Phase 2
Contractor: Kiewit Infrastructure West Company
10704 Shoemaker Avenue
Santa Fe Springs, CA 90670-4024
Project ID: FCC0001313
Federal Number(s): None
Original Contract: $7,493,500.00
Awarded: 5/7/2024
Period Ending: 5/5/2025
Board Accepted: 8/19/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
40FINAL ACCEPTANCE TESTING - BUTTERFLY VALVE 11.00EA 1.00 0.900.10$50,000.00$5,000.00
41FINAL ACCEPTANCE TESTING - BUTTERFLY VALVE 21.00EA 1.00 0.900.10$50,000.00$5,000.00
42FINAL ACCEPTANCE TESTING - BUTTERFLY VALVE 31.00EA 1.00 0.900.10$50,000.00$5,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $8,121,382.00 $8,105,382.00 $16,000.00
Retained $406,069.10 $405,269.10 $800.00
Deducted $0.00 $0.00 $0.00
Due $7,715,312.90 $7,700,112.90 $15,200.00



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.