| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| S-2 | FOUNDATION CHANGE | | T&M |
8,113.75
| 0.00 | 8,113.75 | $1.00 | $8,113.75 |
| S-3 | POLE TYPE 29 & 50' MAST ARM | | LS |
1.00
| 0.00 | 1.00 | $26,886.25 | $26,886.25 |
| S-4 | OPEN TRENCHING AND CONDUIT INSTALLATION - PHASE1 | | T&M |
12,111.18
| 0.00 | 12,111.18 | $1.00 | $12,111.18 |
| S-5 | OPEN TRENCHING AND CONDUIT INSTALLATION - PHASE1 | | T&M |
11,148.28
| 0.00 | 11,148.28 | $1.00 | $11,148.28 |