Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Washington Boulevard TSSP - Atlantic Boulevard to Whittier Boulevard
Contractor: Crosstown Electrical & Data, Inc.
5454 Diaz Street
Irwindale, CA 91706
Project ID: TSM0010285
Federal Number(s): None
Original Contract: $1,990,667.00
Awarded: 2/1/2024
Period Ending: 4/20/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 0.36 0.180.18$5,000.00$900.00
5IMPLEMENTATION OF BMPS1.00LS 0.32 0.160.16$2,500.00$400.00
6MOBILIZATION1.00LS 0.45 0.360.09$85,000.00$7,650.00
7EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $18,750)18,750.00AL 9,600.00 0.009,600.00$1.00$9,600.00
181-1/2" CONDUIT (SCH 80 PVC)40.00LF 20.00 0.0020.00$122.00$2,440.00
203" CONDUIT (SCH 80 PVC)740.00LF 740.00 640.00100.00$140.00$14,000.00
31NO. 5 PULL BOX INCL PCC COVER1.00EA 1.00 0.001.00$1,460.00$1,460.00
32NO. 6 PULL BOX INCL PCC COVER22.00EA 15.00 13.002.00$1,705.00$3,410.00
48REMOVE TYPE 1 FOUNDATION4.00EA 1.00 0.001.00$1,765.00$1,765.00
81TYPE 1 STANDARD1.00EA 1.00 0.001.00$1,665.00$1,665.00
82TYPE 15 STANDARD4.00EA 3.00 0.003.00$4,700.00$14,100.00
85TYPE 26 STANDARD3.00EA 2.00 0.002.00$13,075.00$26,150.00
87TYPE 1 STANDARD FOUNDATION1.00EA 1.00 0.001.00$2,435.00$2,435.00
88TYPE 15 STANDARD FOUNDATION6.00EA 3.00 0.003.00$3,050.00$9,150.00
92TYPE 29 STANDARD FOUNDATION1.00EA 1.00 0.001.00$6,695.00$6,695.00
10212' LUMINAIRE MAST ARM9.00EA 3.00 0.003.00$1,400.00$4,200.00
142TRAFFIC CONTROL1.00LS 0.50 0.400.10$115,000.00$11,500.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $422,507.78 $304,987.78 $117,520.00
Retained $21,125.38 $15,249.38 $5,876.00
Deducted $0.00 $0.00 $0.00
Due $401,382.40 $289,738.40 $111,644.00



Contact Office Engineer