| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.50
| 0.40 | 0.10 | $5,000.00 | $500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.50
| 0.40 | 0.10 | $5,000.00 | $500.00 |
| 6 | OFFICE FACILITIES | 5.00 | MTH |
2.25
| 1.25 | 1.00 | $7,500.00 | $7,500.00 |
| 7 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $145,000.00 | $7,250.00 |
| 8 | CLEARING AND GRUBBING | 1.00 | LS |
0.70
| 0.60 | 0.10 | $10,000.00 | $1,000.00 |
| 9 | CROWN REDUCTION W/ROOT PRUNING, TREE (13" - 24" DIAMETER) | 10.00 | EA |
2.00
| 1.00 | 1.00 | $800.00 | $800.00 |
| 10 | REMOVE EXISTING CHAIN LINK FENCE | 4,200.00 | LF |
3,119.00
| 1,000.00 | 2,119.00 | $6.50 | $13,773.50 |
| 11 | CONCRETE REMOVAL (REINFORCED) | 15.00 | CY |
3.75
| 2.25 | 1.50 | $500.00 | $750.00 |
| 13 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.40 | 0.10 | $25,000.00 | $2,500.00 |
| 14 | LANDSCAPING | 1.00 | LS |
0.30
| 0.20 | 0.10 | $165,000.00 | $16,500.00 |
| 15 | IRRIGATION SYSTEM | 1.00 | LS |
0.70
| 0.60 | 0.10 | $318,500.00 | $31,850.00 |
| 17 | TREE PROTECTION FENCING | 1.00 | LS |
0.80
| 0.70 | 0.10 | $21,000.00 | $2,100.00 |
| 19 | TUBULAR STEEL FENCE, 8' HIGH | 3,734.00 | LF |
2,812.00
| 500.00 | 2,312.00 | $270.00 | $624,240.00 |
| 23 | TUBULAR STEEL VEHICULAR SLIDING GATE, 8' HIGH | 2.00 | EA |
1.00
| 0.00 | 1.00 | $32,000.00 | $32,000.00 |
|