Los Angeles County Public Works
Project Management Division III
Progress Payment 14
Project Name:
Owen Tank Replacement
Contractor:
GMZ Engineering, Inc.
5655 Lindero Canyon Road #430
Westlake Village
,
CA
91362
Project ID:
WWD2900041
Federal Number(s):
None
Original Contract:
$4,427,975.00
Awarded:
12/13/2022
Period Ending:
3/19/2025
Board Accepted:
7/23/2025
Item No.
Description
Bid Qty
Units
Total Qty.
Previous Qty.
Current Qty.
Unit Price
Current Amount
5
IMPLEMENTATION OF BMPS
1.00
LS
1.00
0.99
0.01
$35,000.00
$350.00
38
ELECTRICAL WORK
1.00
LS
1.00
0.90
0.10
$550,000.00
$55,000.00
S-14
REVISE RADIO AND ANTENA
LS
1.00
0.00
1.00
$5,929.57
$5,929.57
S-19
DELIVERY DELAY POSTPONEMENT
DAYS
168.00
61.00
107.00
$0.00
$0.00
DEDUCTION DETAIL
There are NO deductions this period
FINANCIAL SUMMARY
Total
Previous
Current
Earned
$4,715,962.94
$4,654,683.37
$61,279.57
Retained
$235,798.18
$232,734.17
$3,064.01
Deducted
$0.00
$0.00
$0.00
Due
$4,480,164.76
$4,421,949.20
$58,215.56
Contact Office Engineer
Contractor Copy
P
Please consider the environment before printing this report.