| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | OFFICE FACILITIES | 6.00 | MO |
4.00
| 3.00 | 1.00 | $5,000.00 | $5,000.00 |
| 3 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.60
| 0.45 | 0.15 | $10,000.00 | $1,500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.60
| 0.45 | 0.15 | $25,000.00 | $3,750.00 |
| 5 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MO |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 15 | PCC CURB, TYPE A1-6 | 877.00 | LF |
822.50
| 585.50 | 237.00 | $65.00 | $15,405.00 |
| 26 | ELECTRICAL WORK | 1.00 | LS |
0.489
| 0.339 | 0.15 | $350,000.00 | $52,500.00 |
| 29 | AGRONOMIC SOIL REPORTS | 6.00 | EA |
6.00
| 0.00 | 6.00 | $300.00 | $1,800.00 |
| 30 | UNCLASSIFIED EXCAVATION LANDSCAPE | 1,207.00 | CY |
1,207.00
| 1,126.00 | 81.00 | $100.00 | $8,100.00 |
| 31 | CLASS "D" BIOSWALE SOIL | 741.00 | CY |
737.00
| 357.00 | 380.00 | $150.00 | $57,000.00 |
| 36 | DECORATIVE BOULDERS | 79.00 | EA |
30.00
| 0.00 | 30.00 | $450.00 | $13,500.00 |
| 37 | LID RIVER ROCK COBBLE SWALE | 46.00 | TON |
25.00
| 0.00 | 25.00 | $200.00 | $5,000.00 |
| 40 | IRRIGATION | 1.00 | LS |
0.192
| 0.152 | 0.04 | $80,000.00 | $3,200.00 |