| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.05
| 0.00 | 0.05 | $45,000.00 | $2,250.00 |
| 5 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 6 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.05
| 0.00 | 0.05 | $135,000.00 | $6,750.00 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.05
| 0.00 | 0.05 | $10,000.00 | $500.00 |
| 11 | PREPARATION OF SOIL MANAGEMENT PLAN (STIPULATED UNIT PRICE $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 12 | IMPLEMENTATION OF SOIL MANAGEMENT PLAN | 1.00 | LS |
0.25
| 0.00 | 0.25 | $25,000.00 | $6,250.00 |
| 13 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 16 | OFFICE FACILITIES | 25.00 | MTH |
1.00
| 0.00 | 1.00 | $15,000.00 | $15,000.00 |
| 18 | TRAFFIC CONTROL | 1.00 | LS |
0.05
| 0.00 | 0.05 | $1,700,000.00 | $85,000.00 |
| 19 | CLEARING AND GRUBBING | 1.00 | LS |
0.25
| 0.00 | 0.25 | $100,000.00 | $25,000.00 |
| 24 | STUMP REMOVAL ONLY (13"-24" DIAMETER) | 2.00 | EA |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 25 | TREE REMOVAL (13"-24" DIAMETER) | 87.00 | EA |
49.00
| 0.00 | 49.00 | $550.00 | $26,950.00 |
| 27 | CONCRETE REMOVAL (NON-REINFORCED) | 3,340.00 | CY |
215.03
| 0.00 | 215.03 | $240.00 | $51,607.20 |
| 29 | UNCLASSIFIED EXCAVATION | 23,912.00 | CY |
341.04
| 0.00 | 341.04 | $100.00 | $34,104.00 |
| 31 | CRUSHED MISCELLANEOUS BASE | 4,311.00 | CY |
288.12
| 0.00 | 288.12 | $235.00 | $67,708.20 |
| 34 | AC PAVEMENT(PATCH BACK) | 4,524.00 | TON |
32.49
| 0.00 | 32.49 | $180.00 | $5,848.20 |
| 35 | AC PAVEMENT(DRIVEWAYS) | 25.00 | TON |
4.00
| 0.00 | 4.00 | $700.00 | $2,800.00 |
| 37 | RECONSTRUCT MANHOLE | 2.00 | EA |
1.00
| 0.00 | 1.00 | $4,450.00 | $4,450.00 |
| 47 | PCC CURB, TYPE A1-VAR | 876.00 | LF |
119.00
| 0.00 | 119.00 | $40.00 | $4,760.00 |
| 49 | PCC CURB & GUTTER, TYPE A2-8 | 2,067.00 | LF |
348.90
| 0.00 | 348.90 | $44.00 | $15,351.60 |
| 57 | PCC WALK & DRIVEWAYS, 4" THICK | 38,431.00 | SF |
1,074.00
| 0.00 | 1,074.00 | $8.50 | $9,129.00 |
| 58 | PCC CURB RAMPS | 150.00 | CY |
17.14
| 0.00 | 17.14 | $1,200.00 | $20,568.00 |
| 59 | PCC DRIVEWAYS, 6" THICK | 4,910.00 | SF |
1,000.00
| 0.00 | 1,000.00 | $13.00 | $13,000.00 |
| 60 | DETECTABLE WARNING SURFACE | 960.00 | SF |
72.00
| 0.00 | 72.00 | $60.00 | $4,320.00 |
| 63 | LOCAL DEPRESSION PER STD PLAN 313, CASE F | 2.00 | EA |
0.50
| 0.00 | 0.50 | $1,800.00 | $900.00 |
| 72 | 2" CONDUIT (SCH 80 PVC) | 3,735.00 | LF |
1,004.00
| 0.00 | 1,004.00 | $70.00 | $70,280.00 |
| 73 | 3" CONDUIT (SCH 80 PVC) | 4,215.00 | LF |
596.00
| 0.00 | 596.00 | $100.00 | $59,600.00 |
| 202 | FLASHING ARROW SIGN | 2.00 | EA |
1.00
| 0.00 | 1.00 | $30,000.00 | $30,000.00 |
| 203 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
1.00
| 0.00 | 1.00 | $60,000.00 | $60,000.00 |
| 228 | PCC PAVEMENT (HIGH EARLY STRENGTH) | 456.00 | CY |
31.48
| 0.00 | 31.48 | $535.00 | $16,841.80 |
| 246 | COMPOSITE TYPE 2 PULL BOX INCL COVER | 27.00 | EA |
8.00
| 0.00 | 8.00 | $2,200.00 | $17,600.00 |
| 247 | COMPOSITE TYPE 3 PULL BOX INCL COVER | 71.00 | EA |
5.00
| 0.00 | 5.00 | $2,650.00 | $13,250.00 |
| 261 | 2 INCH DIAMETER NON-METALLIC PVC SCHEDULE 80 BRANCH CONDUIT, FITTINGS AND SUPPORTS | 5,124.00 | LF |
741.00
| 0.00 | 741.00 | $65.00 | $48,165.00 |
| S-2 | TEMP TRAFFIC SIGNAL PLAN | | T&M |
7,820.88
| 0.00 | 7,820.88 | $1.00 | $7,820.88 |
| S-5 | SWRCB PERMIT FEE | | LS |
1.00
| 0.00 | 1.00 | $773.95 | $773.95 |
|