| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
15.00
| 8.00 | 7.00 | $500.00 | $3,500.00 |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 0.99 | 0.01 | $23,000.00 | $230.00 |
| 6 | OFFICE FACILITIES | 9.00 | MTH |
15.00
| 9.00 | 6.00 | $2,600.00 | $15,600.00 |
| 9 | TREE REMOVAL (13"-24" DIAMETER) | 4.00 | EA |
8.00
| 5.00 | 3.00 | $3,000.00 | $9,000.00 |
| 10 | TREE REMOVAL (25"+ DIAMETER) | 4.00 | EA |
8.00
| 7.00 | 1.00 | $6,000.00 | $6,000.00 |
| 15 | CONCRETE REMOVAL (NON-REINFORCED) | 3,141.00 | CY |
2,702.00
| 2,550.89 | 151.11 | $200.00 | $30,222.00 |
| 20 | COLD MILL AC PAVEMENT (2" - 3") | 1,422,410.00 | SF |
1,448,115.00
| 1,422,410.00 | 25,705.00 | $0.43 | $11,053.15 |
| 23 | AC PAVEMENT(PATCH BACK) | 1,008.00 | TON |
815.00
| 472.46 | 342.54 | $200.00 | $68,508.00 |
| 27 | PCC PAVEMENT | 310.00 | CY |
349.82
| 310.00 | 39.82 | $600.00 | $23,892.00 |
| 28 | PCC CROSSWALK PER DETAIL G, SHEET 11 | 8.00 | CY |
12.11
| 8.00 | 4.11 | $1,200.00 | $4,932.00 |
| 29 | ASPHALT RUBBER AND AGGREGATE MEMBRANE | 61,643.00 | SY |
62,940.00
| 61,643.00 | 1,297.00 | $7.00 | $9,079.00 |
| 34 | CURB DRAIN PER STD PLAN 150, N=1, CASE 3 INLET | 16.00 | EA |
29.00
| 16.00 | 13.00 | $500.00 | $6,500.00 |
| 35 | CURB DRAIN PER STD PLAN 150, N=2, CASE 3 INLET | 2.00 | EA |
6.00
| 2.00 | 4.00 | $600.00 | $2,400.00 |
| 36 | CONCRETE SLOUGH WALL | 1.00 | CY |
1.15
| 1.00 | 0.15 | $6,000.00 | $900.00 |
| 42 | PCC CURB & GUTTER, TYPE A2-VAR, W=VAR | 25.00 | LF |
223.50
| 25.00 | 198.50 | $65.00 | $12,902.50 |
| 45 | PCC CURB RAMPS | 461.00 | CY |
416.83
| 460.61 | -43.78 | $1,200.00 | ($52,536.00) |
| 46 | PCC DRIVEWAYS, 6" THICK | 1,697.00 | SF |
2,261.68
| 1,697.00 | 564.68 | $13.00 | $7,340.84 |
| 49 | CROSS GUTTER (MOD) | 143.00 | CY |
151.20
| 143.00 | 8.20 | $700.00 | $5,740.00 |
| 55 | ADJUST PULL BOX | 113.00 | EA |
137.00
| 113.00 | 24.00 | $500.00 | $12,000.00 |
| 65 | RECONFIG VIDEO DETECTION ZONE - 1 CAMERA | 4.00 | EA |
6.00
| 4.00 | 2.00 | $1,300.00 | $2,600.00 |
| 66 | SALVAGE EQUIPMENT | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 67 | INSTALL FIRE HYDRANT LOCATION RPM | 19.00 | EA |
47.00
| 10.00 | 37.00 | $15.00 | $555.00 |
| 68 | DETAIL 9 (THERMOPLASTIC) | 22,402.00 | LF |
22,248.00
| 12,000.00 | 10,248.00 | $0.42 | $4,304.16 |
| 69 | DETAIL 22 (THERMOPLASTIC) | 12,632.00 | LF |
12,632.00
| 6,000.00 | 6,632.00 | $0.95 | $6,300.40 |
| 70 | DETAIL 24 (THERMOPLASTIC) | 200.00 | LF |
206.00
| 100.00 | 106.00 | $0.55 | $58.30 |
| 71 | DETAIL 27B (THERMOPLASTIC) | 338.00 | LF |
313.00
| 150.00 | 163.00 | $0.55 | $89.65 |
| 72 | DETAIL 29 (THERMOPLASTIC) | 2,605.00 | LF |
1,968.00
| 1,300.00 | 668.00 | $1.90 | $1,269.20 |
| 73 | DETAIL 32 (THERMOPLASTIC) | 3,606.00 | LF |
4,502.00
| 1,800.00 | 2,702.00 | $1.90 | $5,133.80 |
| 74 | DETAIL 38A (THERMOPLASTIC) | 7,249.00 | LF |
8,094.00
| 3,500.00 | 4,594.00 | $2.17 | $9,968.98 |
| 75 | INSTALL DETAIL 39A MODIFIED (4' LINE WITH 4' SKIP) (THERMOPLASTIC) | 390.00 | LF |
370.00
| 200.00 | 170.00 | $3.00 | $510.00 |
| 76 | DETAIL 40 (THERMOPLASTIC) | 55.00 | LF |
0.00
| 25.00 | -25.00 | $3.00 | ($75.00) |
| 77 | 4" STRIPING (THERMOPLASTIC) | 14,266.00 | LF |
14,000.00
| 7,000.00 | 7,000.00 | $0.55 | $3,850.00 |
| 78 | 4" YELLOW STRIPING (THERMOPLASTIC) | 16.00 | LF |
0.00
| 8.00 | -8.00 | $0.55 | ($4.40) |
| 79 | 12" STRIPING (THERMOPLASTIC) | 7,698.00 | LF |
9,165.00
| 4,000.00 | 5,165.00 | $2.05 | $10,588.25 |
| 80 | 12" WHITE CHEVRON STRIPING (THERMOPLASTIC) | 44.00 | LF |
0.00
| 20.00 | -20.00 | $3.00 | ($60.00) |
| 81 | 12" YELLOW DIAGONAL STRIPING (THERMOPLASTIC) | 247.00 | LF |
227.00
| 175.00 | 52.00 | $3.00 | $156.00 |
| 82 | 24" STRIPING (THERMOPLASTIC) | 17,434.00 | LF |
19,074.87
| 8,000.00 | 11,074.87 | $4.10 | $45,406.97 |
| 83 | 24" YELLOW STRIPING (THERMOPLASTIC) | 1,293.00 | LF |
3,160.00
| 600.00 | 2,560.00 | $4.10 | $10,496.00 |
| 84 | PARKING STRIPING (THERMOPLASTIC) | 1,921.00 | LF |
822.00
| 1,000.00 | -178.00 | $2.40 | ($427.20) |
| 85 | PAVEMENT MARKINGS (THERMOPLASTIC) | 4,704.00 | SF |
3,928.00
| 2,200.00 | 1,728.00 | $5.90 | $10,195.20 |
| 86 | BICYCLE PAVEMENT MARKING ON GREEN BACKGROUND | 21.00 | SF |
42.00
| 10.00 | 32.00 | $25.00 | $800.00 |
| 87 | CURB MARKINGS (ONE-COAT PAINT) | 16.00 | LF |
0.00
| 8.00 | -8.00 | $5.00 | ($40.00) |
| 88 | REMOVE STRIPING (THERMOPLASTIC) | 1,704.00 | LF |
1,933.00
| 1,000.00 | 933.00 | $2.05 | $1,912.65 |
| 89 | REMOVE PAVEMENT MARKINGS (THERMOPLASTIC) | 338.00 | SF |
3,549.50
| 150.00 | 3,399.50 | $3.65 | $12,408.18 |
| 90 | SIGN PANEL | 108.00 | EA |
180.00
| 108.00 | 72.00 | $115.00 | $8,280.00 |
| 91 | SIGN POST (ROADSIDE SIGN) | 40.00 | EA |
35.00
| 30.00 | 5.00 | $165.00 | $825.00 |
| 92 | RELOCATE SIGN | 23.00 | EA |
23.00
| 9.00 | 14.00 | $44.00 | $616.00 |
| 93 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.99 | 0.01 | $211,000.00 | $2,110.00 |
| 98 | FURNISH AND PLANT 24" BOX TREE | 8.00 | EA |
11.00
| 8.00 | 3.00 | $900.00 | $2,700.00 |
| S-3 | TRAFFIC SIGNAL COMPONENTS | | T&M |
660,938.85
| 653,142.73 | 7,796.12 | $1.00 | $7,796.12 |
| S-4 | WHEELCHAIR RAMPS | | NEG |
0.00
| 0.20 | -0.20 | $38,332.75 | ($7,666.55) |
| S-4A | RECONSTRUCT RESTAURANT COUNTER | | LS |
1.00
| 0.00 | 1.00 | $7,666.55 | $7,666.55 |
| S-7 | WATER VALVE ADJUSTMENTS | | LS |
1.00
| 0.00 | 1.00 | $32,900.00 | $32,900.00 |
| S-8 | PROJECT DELAY ADJUSTMENT | | LS |
1.00
| 0.00 | 1.00 | $42,000.00 | $42,000.00 |
|