| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 2.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.75
| 0.00 | 0.75 | $5,000.00 | $3,750.00 |
| 5 | MOBILIZATION | 1.00 | LS |
1.00
| 0.00 | 1.00 | $60,000.00 | $60,000.00 |
| 6 | EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $15,000) | 15,000.00 | AL |
15,000.00
| 0.00 | 15,000.00 | $1.00 | $15,000.00 |
| 7 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 8 | SIGN PANEL | 625.00 | EA |
615.00
| 0.00 | 615.00 | $240.00 | $147,600.00 |
| 9 | REMOVE SIGN POST | 63.00 | EA |
63.00
| 0.00 | 63.00 | $150.00 | $9,450.00 |
| 10 | REMOVE SIGN PANEL | 112.00 | EA |
112.00
| 0.00 | 112.00 | $100.00 | $11,200.00 |
| 11 | SIGN POST (ROADSIDE SIGN) | 514.00 | EA |
514.00
| 0.00 | 514.00 | $350.00 | $179,900.00 |
| 12 | VEHICLE SPEED FEEDBACK SIGN (COMPLETE) | 4.00 | EA |
3.00
| 0.00 | 3.00 | $18,500.00 | $55,500.00 |
| 13 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.00 | 0.90 | $88,000.00 | $79,200.00 |
| 14 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
2.00
| 0.00 | 2.00 | $6,000.00 | $12,000.00 |