Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Bouquet Canyon Road - 638 Feet North of MM 16.43 to 1145 Feet North of MM 3.52
Contractor: Sterndahl Enterprises, LLC
11861 Branford Street
Sun Valley, CA 91352-1032
Project ID: TDS0001635
Federal Number(s): 5953 (779)
Original Contract: $614,050.00
Awarded: 9/27/2024
Period Ending: 6/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)2.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF BMPS1.00LS 0.75 0.000.75$5,000.00$3,750.00
5MOBILIZATION1.00LS 1.00 0.001.00$60,000.00$60,000.00
6EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $15,000)15,000.00AL 15,000.00 0.0015,000.00$1.00$15,000.00
7CLEARING AND GRUBBING1.00LS 1.00 0.001.00$5,000.00$5,000.00
8SIGN PANEL625.00EA 615.00 0.00615.00$240.00$147,600.00
9REMOVE SIGN POST63.00EA 63.00 0.0063.00$150.00$9,450.00
10REMOVE SIGN PANEL112.00EA 112.00 0.00112.00$100.00$11,200.00
11SIGN POST (ROADSIDE SIGN)514.00EA 514.00 0.00514.00$350.00$179,900.00
12VEHICLE SPEED FEEDBACK SIGN (COMPLETE)4.00EA 3.00 0.003.00$18,500.00$55,500.00
13TRAFFIC CONTROL1.00LS 0.90 0.000.90$88,000.00$79,200.00
14CHANGEABLE MESSAGE SIGN2.00EA 2.00 0.002.00$6,000.00$12,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $581,600.00 $0.00 $581,600.00
Retained $29,080.00 $0.00 $29,080.00
Deducted $0.00 $0.00 $0.00
Due $552,520.00 $0.00 $552,520.00



Contact Office Engineer
Contractor Copy  