| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 7.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.20
| 0.00 | 0.20 | $30,000.00 | $6,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.20
| 0.00 | 0.20 | $30,000.00 | $6,000.00 |
| 6 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.30
| 0.00 | 0.30 | $100,000.00 | $30,000.00 |
| 7 | PREPARATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.20
| 0.00 | 0.20 | $5,000.00 | $1,000.00 |
| 9 | PREPARATION OF THE SITE SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 12 | PREPARATION OF THE NOISE MITIGATION PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 16 | OFFICE FACILITIES | 8.00 | MTH |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| 17 | MOBILIZATION | 1.00 | LS |
0.75
| 0.00 | 0.75 | $100,000.00 | $75,000.00 |
| 19 | 12" WATERMAIN, .25" THICK STL, CML & CMC, WELDED | 2,146.00 | LF |
600.00
| 0.00 | 600.00 | $650.00 | $390,000.00 |
| 25 | RECONNECT EXISTING WATER SERVICE WITH NEW METER BOX AND LID | 17.00 | EA |
2.00
| 0.00 | 2.00 | $8,000.00 | $16,000.00 |
| 40 | INITIAL VIDEO INSPECTION | 1.00 | LS |
0.30
| 0.00 | 0.30 | $5,000.00 | $1,500.00 |
| 42 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.00 | 0.30 | $100,000.00 | $30,000.00 |