| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $2,500.00 | $0.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
4.00
| 4.00 | 0.00 | $500.00 | $0.00 |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 1.00 | 0.00 | $10,000.00 | $0.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 1.00 | 0.00 | $60,000.00 | $0.00 |
| 6 | CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $25,000) | 25,000.00 | AL |
36,447.19
| 36,447.19 | 0.00 | $1.00 | $0.00 |
| 7 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $3,000.00 | $0.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
1.00
| 1.00 | 0.00 | $25,000.00 | $0.00 |
| 9 | REMOVAL AND DISPOSAL OF LBP/LCP WASTE | 1.00 | LS |
1.00
| 1.00 | 0.00 | $90,000.00 | $0.00 |
| 10 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $3,000.00 | $0.00 |
| 11 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
1.00
| 1.00 | 0.00 | $25,000.00 | $0.00 |
| 12 | OFFICE FACILITIES | 5.00 | MTH |
5.00
| 5.00 | 0.00 | $20,000.00 | $0.00 |
| 13 | MOBILIZATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $300,000.00 | $0.00 |
| 14 | OPERATIONAL TESTS | 1.00 | LS |
1.00
| 0.98 | 0.02 | $60,000.00 | $1,200.00 |
| 15 | DEMOLITION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $390,000.00 | $0.00 |
| 16 | TRASH RACK | 1.00 | LS |
1.00
| 1.00 | 0.00 | $400,000.00 | $0.00 |
| 17 | MISCELLANEOUS MECHANICAL WORKS | 1.00 | LS |
1.00
| 1.00 | 0.00 | $600,000.00 | $0.00 |
| 18 | FURNISH AND INSTALL SUBMERSIBLE PUMP AND ACCESSORIES | 1.00 | LS |
1.00
| 1.00 | 0.00 | $800,000.00 | $0.00 |
| 19 | FURNISH AND INSTALL SUMP PUMP AND ACCESSORIES | 1.00 | LS |
1.00
| 1.00 | 0.00 | $180,000.00 | $0.00 |
| 20 | FURNISH SPARE SUMP PUMP | 3.00 | EA |
3.00
| 3.00 | 0.00 | $30,000.00 | $0.00 |
| 21 | ELECTRICAL WORK FOR WEST TOLEDO PUMP STATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $600,000.00 | $0.00 |
| 22 | ELECTRICAL WORK FOR WEST NEAPOLITAN PUMP STATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $600,000.00 | $0.00 |
| 23 | ELECTRICAL WORK FOR EAST TOLEDO PUMP STATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $600,000.00 | $0.00 |
| 24 | STRUCTURE CONCRETE | 10.00 | CY |
10.00
| 10.00 | 0.00 | $6,000.00 | $0.00 |
| 25 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 261.00 | LF |
261.00
| 261.00 | 0.00 | $200.00 | $0.00 |
| 26 | TRAFFIC HATCH DOOR | 5.00 | EA |
5.00
| 5.00 | 0.00 | $60,000.00 | $0.00 |
| 27 | FRP PLATFORM | 1.00 | LS |
1.00
| 1.00 | 0.00 | $200,000.00 | $0.00 |
| 28 | REMOVE EXISTING CONCRETE | 1.00 | LS |
1.00
| 1.00 | 0.00 | $76,000.00 | $0.00 |
| 29 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 1.00 | 0.00 | $200,000.00 | $0.00 |
| S-1 | EXTENSION OF TIME, PART 1 NTP | | WD |
26.00
| 26.00 | 0.00 | $0.00 | $0.00 |
| S-2 | TRASH RACK DOOR FRAMING MODIFICATIONS | | LS |
1.00
| 1.00 | 0.00 | $1,900.00 | $0.00 |
| S-3 | PUMP FRAME REMOVAL | | LS |
1.00
| 1.00 | 0.00 | $22,500.00 | $0.00 |
| S-4 | WATER LINE RELOCATION | | LS |
1.00
| 1.00 | 0.00 | $27,500.00 | $0.00 |
| S-5 | REPLACE ENTRANCE DOOR FRAMES | | LS |
1.00
| 1.00 | 0.00 | $12,500.00 | $0.00 |
| S-6 | PIPE SUPPORTS | | LS |
1.00
| 1.00 | 0.00 | $9,700.00 | $0.00 |
| S-7 | CONDUIT RELOCATION PER RFI NO. 55 | | LS |
1.00
| 1.00 | 0.00 | $3,500.00 | $0.00 |
| S-8 | DISCHARGE PIPE HANGERS | | LS |
1.00
| 1.00 | 0.00 | $3,200.00 | $0.00 |
| S-9 | ADDITIONAL ASBESTOS REMOVAL | | LS |
1.00
| 1.00 | 0.00 | $3,000.00 | $0.00 |
| S-10 | GENERAL RENTAL FOR WEST NEAPOLITAN | | LS |
1.00
| 1.00 | 0.00 | $1,650.00 | $0.00 |
| S-11 | SUBMERSIBLE PUMP CONDUIT UPSIZE | | LS |
1.00
| 1.00 | 0.00 | $10,000.00 | $0.00 |
| S-12 | ANNUNCIATOR REPROGRAMMING | | LS |
1.00
| 1.00 | 0.00 | $3,850.00 | $0.00 |
| S-13 | PUMP SCHEMATIC CHANGES | | LS |
1.00
| 1.00 | 0.00 | $1,770.00 | $0.00 |
| S-14 | DRAIN PAN PIPE MODIFICATIONS | | LS |
1.00
| 1.00 | 0.00 | $3,000.00 | $0.00 |
| S-15 | BUBBLER PANEL COMPRESSOR REPLACEMENT | | LS |
1.00
| 1.00 | 0.00 | $9,500.00 | $0.00 |
| S-16 | BLOWER COVERS | | LS |
1.00
| 1.00 | 0.00 | $1,500.00 | $0.00 |
| S-17 | EAST TOLEDO MTS CONDUIT | | LS |
1.00
| 1.00 | 0.00 | $7,200.00 | $0.00 |
| S-18 | CONTRACT TIME EXTENSION | | NWD |
233.00
| 0.00 | 233.00 | $0.00 | $0.00 |