| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $60,000.00 | $3,000.00 |
| 2 | OFFICE FACILITIES | 6.00 | MO |
6.00
| 4.00 | 2.00 | $5,000.00 | $10,000.00 |
| 3 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.90
| 0.60 | 0.30 | $10,000.00 | $3,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.90
| 0.60 | 0.30 | $25,000.00 | $7,500.00 |
| 5 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MO |
5.00
| 3.00 | 2.00 | $500.00 | $1,000.00 |
| 9 | AC PAVEMENT(PATCH BACK) | 44.00 | TON |
44.00
| 0.00 | 44.00 | $350.00 | $15,400.00 |
| 11 | CRUSHED MISCELLANEOUS BASE | 54.00 | CY |
53.63
| 34.50 | 19.13 | $100.00 | $1,913.00 |
| 12 | AC PAVEMENT | 4.00 | TON |
4.00
| 0.00 | 4.00 | $500.00 | $2,000.00 |
| 13 | STRUCTURE CONCRETE | 13.00 | CY |
10.00
| 0.00 | 10.00 | $700.00 | $7,000.00 |
| 14 | BAR REINFORCING STEEL | 1,080.00 | LB |
1,080.00
| 0.00 | 1,080.00 | $5.00 | $5,400.00 |
| 16 | STRUCTURAL STEEL | 5,150.00 | LB |
5,150.00
| 1,483.70 | 3,666.30 | $20.00 | $73,326.00 |
| 17 | PERVIOUS CONCRETE, 6" THICK | 2,216.00 | SF |
2,210.537
| 0.00 | 2,210.537 | $30.50 | $67,421.38 |
| 18 | CLEAN & PAINT STRUCTURAL STEEL | 1.00 | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| 26 | ELECTRICAL WORK | 1.00 | LS |
0.589
| 0.489 | 0.10 | $350,000.00 | $35,000.00 |
| 27 | WHEEL STOP | 186.00 | EA |
143.00
| 0.00 | 143.00 | $110.00 | $15,730.00 |
| 28 | PREFAB GUARD BOOTH | 1.00 | LS |
0.30
| 0.0994 | 0.2006 | $150,000.00 | $30,090.00 |
| 31 | CLASS "D" BIOSWALE SOIL | 741.00 | CY |
741.00
| 737.00 | 4.00 | $150.00 | $600.00 |
| 32 | CRUSHED AGGREGATE BASE (CAB) | 41.00 | CY |
41.00
| 0.00 | 41.00 | $120.00 | $4,920.00 |
| 33 | CONCRETE SEATWALL W/ANTI-SKATE BUMPS | 1.00 | LS |
0.90
| 0.00 | 0.90 | $10,000.00 | $9,000.00 |
| 35 | BUS SHELTER | 1.00 | LS |
0.91
| 0.456 | 0.454 | $25,000.00 | $11,350.00 |
| 36 | DECORATIVE BOULDERS | 79.00 | EA |
70.00
| 30.00 | 40.00 | $450.00 | $18,000.00 |
| 37 | LID RIVER ROCK COBBLE SWALE | 46.00 | TON |
46.00
| 25.00 | 21.00 | $200.00 | $4,200.00 |
| 40 | IRRIGATION | 1.00 | LS |
0.232
| 0.192 | 0.04 | $80,000.00 | $3,200.00 |
| S-1A | FURNISH & INSTALL (11) 25' LIGHT POLES (NEGOTIATED) | | LS |
0.55
| 0.00 | 0.55 | $128,598.00 | $70,728.90 |
| S-2 | DRILL PILE HOLES (COP2) | | LF |
96.00
| 0.00 | 96.00 | $68.00 | $6,528.00 |
| S-3 | TIE-IN TO EXISTING 200 AMP METER MAIN | | LS |
0.80
| 0.00 | 0.80 | $26,910.00 | $21,528.00 |
| S-4 | PERMIT WORK COMPENSATION | | LS |
1.00
| 0.00 | 1.00 | $13,312.00 | $13,312.00 |
| S-8 | SAW CUT, SLURRY FILL, AND AC TOP (RFI 024) | | LS |
0.50
| 0.00 | 0.50 | $8,867.00 | $4,433.50 |
| S-9 | REROUTE CONDUIT TO GUARD BOOTH (RFI 017) | | LS |
1.00
| 0.00 | 1.00 | $6,397.00 | $6,397.00 |
| S-12 | TEMPORARY LIGHTING (COP12R1) | | LS |
0.80
| 0.00 | 0.80 | $19,709.00 | $15,767.20 |
| S-13 | TEMPORARY FENCE AND ADDITIONAL MOBILIZATION (COP13) | | LS |
0.75
| 0.00 | 0.75 | $29,573.00 | $22,179.75 |
| S-15 | LADWP CRUSHED ROCK (RFI 031) | | LS |
1.00
| 0.00 | 1.00 | $3,823.00 | $3,823.00 |
|