| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 7.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.30
| 0.20 | 0.10 | $30,000.00 | $3,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.40
| 0.20 | 0.20 | $30,000.00 | $6,000.00 |
| 6 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.40
| 0.30 | 0.10 | $100,000.00 | $10,000.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.40
| 0.20 | 0.20 | $5,000.00 | $1,000.00 |
| 16 | OFFICE FACILITIES | 8.00 | MTH |
2.00
| 1.00 | 1.00 | $25,000.00 | $25,000.00 |
| 17 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $100,000.00 | $20,000.00 |
| 19 | 12" WATERMAIN, .25" THICK STL, CML & CMC, WELDED | 2,146.00 | LF |
888.00
| 600.00 | 288.00 | $650.00 | $187,200.00 |
| 24 | RECONNECT EXISTING WATER SERVICE | 6.00 | EA |
2.00
| 0.00 | 2.00 | $7,000.00 | $14,000.00 |
| 25 | RECONNECT EXISTING WATER SERVICE WITH NEW METER BOX AND LID | 17.00 | EA |
11.00
| 2.00 | 9.00 | $8,000.00 | $72,000.00 |
| 29 | BUTTERFLY VALVE, 250 PSI WWP, 12" | 9.00 | EA |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| 40 | INITIAL VIDEO INSPECTION | 1.00 | LS |
0.50
| 0.30 | 0.20 | $5,000.00 | $1,000.00 |
| 42 | TRAFFIC CONTROL | 1.00 | LS |
0.40
| 0.30 | 0.10 | $100,000.00 | $10,000.00 |
| S-2 | TRENCH BACKFILL SLURRY | | LS |
1.00
| 0.00 | 1.00 | $2,100.00 | $2,100.00 |
| S-4 | UNFORESEEN SUBSURFACE SLURRY | | T&M |
999.90
| 0.00 | 999.90 | $1.00 | $999.90 |
| S-5 | METER BOX WATER INTRUSION | | T&M |
904.07
| 0.00 | 904.07 | $1.00 | $904.07 |
| S-6 | EXPLORATORY EXCAVATION AT CASTLE ROCK | | EA |
1.00
| 0.00 | 1.00 | $1,400.00 | $1,400.00 |