| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
2.00
| 0.00 | 2.00 | $500.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.15
| 0.00 | 0.15 | $18,750.00 | $2,812.50 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.15
| 0.00 | 0.15 | $93,750.00 | $14,062.50 |
| 6 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.15
| 0.00 | 0.15 | $37,500.00 | $5,625.00 |
| 8 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.25
| 0.00 | 0.25 | $14,950.00 | $3,737.50 |
| 15 | OFFICE FACILITIES | 6.00 | MTH |
0.50
| 0.00 | 0.50 | $4,375.00 | $2,187.50 |
| 20 | ELECTRICAL | 1.00 | LS |
0.085
| 0.00 | 0.085 | $487,566.00 | $41,443.11 |
| 32 | REMOVAL OF EXISTING STEEL STRUCTURES | 1.00 | LS |
0.25
| 0.00 | 0.25 | $30,625.00 | $7,656.25 |