Los Angeles County Public Works
Project Management Division III
Progress Payment 2
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 7/7/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 3.00 2.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.35 0.150.20$18,750.00$3,750.00
5IMPLEMENTATION OF BMPS1.00LS 0.35 0.150.20$93,750.00$18,750.00
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.35 0.150.20$37,500.00$7,500.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.50 0.250.25$14,950.00$3,737.50
10REMOVAL AND DISPOSAL OF LCP WASTE1.00LS 0.25 0.000.25$28,750.00$7,187.50
11MOBILIZATION1.00LS 0.50 0.000.50$68,750.00$34,375.00
13STRUCTURAL STEEL7,390.00LB 1,995.00 0.001,995.00$32.00$63,840.00
15OFFICE FACILITIES6.00MTH 1.50 0.501.00$4,375.00$4,375.00
20ELECTRICAL1.00LS 0.36 0.0850.275$487,566.00$134,080.65
22MECHANICAL DEMOLITION1.00LS 0.50 0.000.50$29,875.00$14,937.50
31TEMPORARY BYPASS1.00LS 0.10 0.000.10$59,925.00$5,992.50
32REMOVAL OF EXISTING STEEL STRUCTURES1.00LS 0.92 0.250.67$30,625.00$20,518.75
S-1CRANE CERTIFICATION LS 1.00 0.001.00$2,200.00$2,200.00
S-3PLUG TRANSITION STRUCTURE LS 0.30 0.000.30$27,000.00$8,100.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $416,868.76 $87,024.36 $329,844.40
Retained $20,843.44 $4,351.22 $16,492.22
Deducted $0.00 $0.00 $0.00
Due $396,025.32 $82,673.14 $313,352.18



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.