Los Angeles County Public Works
Project Management Division III
Progress Payment 11
Project Name: Olympic Boulevard TSSP - Indiana Street to Montebello Boulevard
Contractor: California Professional Engineering, Inc.
19062 San Jose Avenue
La Puente, CA 91748
Project ID: TSM0010287
Federal Number(s): None
Original Contract: $2,514,601.72
Awarded: 6/22/2023
Period Ending: 7/20/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)11.00MTH 10.00 9.001.00$500.00$500.00
19METAL HAND RAILINGS PER STD PLAN 60665.00LF 35.00 0.0035.00$300.00$10,500.00
242-PAIR DETECTOR LEAD-IN CABLE1,055.00LF 740.00 658.0082.00$3.75$307.50
28#6 WIRE3,030.00LF 1,308.00 596.00712.00$2.80$1,993.60
34INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT1,800.00LF 1,738.00 0.001,738.00$15.00$26,070.00
36REMOVE TYPE 337 CABINET5.00EA 4.00 2.002.00$500.00$1,000.00
45REMOVE VEHICLE HEAD (COMPLETE)117.00EA 116.00 115.001.00$150.00$150.00
49REMOVE PEDESTRIAN PUSH BUTTON PLATE31.00EA 23.00 22.001.00$10.00$10.00
51REMOVE TYPE 337 CABINET FOUNDATION5.00EA 4.00 1.003.00$2,200.00$6,600.00
62RELOCATE CONTROLLER6.00EA 4.00 3.001.00$750.00$750.00
70GPS UTB UNIT AND ANTENNA11.00EA 6.00 5.001.00$1,572.00$1,572.00
105PEDESTRIAN PUSH BUTTON65.00EA 29.00 25.004.00$3,658.00$14,632.00
106PEDESTRIAN PUSH BUTTON PLATE96.00EA 41.00 28.0013.00$25.00$325.00
115VIDEO/RADAR DETECTION SYSTEM WITH 17" LCD MONITOR DRAWER (COMPLETE) - OLYMPIC BL @ GERHART AV1.00EA 1.00 0.500.50$52,000.00$26,000.00
117RADAR DETECTION SYSTEM (COMPLETE) - OLYMPIC BL @ MAPLE AV1.00EA 1.00 0.001.00$53,400.00$53,400.00
119REMOVE STRIPING AND MARKINGS (THERMOPLASTIC)3,350.00SF 3,350.00 0.003,350.00$5.67$18,994.50
120PAVEMENT MARKINGS (TWO-COAT PAINT)15.00SF 15.00 0.0015.00$6.72$100.80
1214" STRIPING (TWO-COAT PAINT)70.00LF 20.00 0.0020.00$4.09$81.80
12212" STRIPING (TWO-COAT PAINT)510.00LF 510.00 0.00510.00$3.33$1,698.30
12312" STRIPING (THERMOPLASTIC)420.00LF 404.00 0.00404.00$3.33$1,345.32
12424" STRIPING (TWO-COAT PAINT)790.00LF 702.00 0.00702.00$7.83$5,496.66
12524" STRIPING (THERMOPLASTIC)3,250.00LF 3,237.00 0.003,237.00$7.83$25,345.71
126DETAIL 21 (TWO-COAT PAINT)160.00LF 160.00 0.00160.00$4.09$654.40
127RED CURB171.00LF 171.00 0.00171.00$6.82$1,166.22
129SIGN PANEL3.00EA 3.00 0.003.00$140.40$421.20
130INSTALL SIGN ON POST2.00EA 2.00 0.002.00$181.35$362.70
S-3TROUBLESHOOT RED FAIL T&M 2,947.86 0.002,947.86$1.00$2,947.86
S-5POLE RELOCATION & ADDITIONAL WORK LS 1.00 0.001.00$18,000.00$18,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,993,243.84 $1,772,818.27 $220,425.57
Retained $99,662.21 $88,640.92 $11,021.29
Deducted $0.00 $0.00 $0.00
Due $1,893,581.63 $1,684,177.35 $209,404.28



Contact Office Engineer