| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.10
| 0.05 | 0.05 | $45,000.00 | $2,250.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.10
| 0.05 | 0.05 | $135,000.00 | $6,750.00 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.10
| 0.05 | 0.05 | $10,000.00 | $500.00 |
| 16 | OFFICE FACILITIES | 25.00 | MTH |
2.00
| 1.00 | 1.00 | $15,000.00 | $15,000.00 |
| 17 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $2,600,000.00 | $1,300,000.00 |
| 18 | TRAFFIC CONTROL | 1.00 | LS |
0.10
| 0.05 | 0.05 | $1,700,000.00 | $85,000.00 |
| 27 | CONCRETE REMOVAL (NON-REINFORCED) | 3,340.00 | CY |
691.14
| 215.03 | 476.11 | $240.00 | $114,266.40 |
| 28 | CONCRETE REMOVAL (REINFORCED) | 11.00 | CY |
1.50
| 0.00 | 1.50 | $900.00 | $1,350.00 |
| 29 | UNCLASSIFIED EXCAVATION | 23,912.00 | CY |
642.82
| 341.04 | 301.78 | $100.00 | $30,178.00 |
| 31 | CRUSHED MISCELLANEOUS BASE | 4,311.00 | CY |
672.87
| 288.12 | 384.75 | $235.00 | $90,416.25 |
| 32 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 301.00 | CY |
30.00
| 0.00 | 30.00 | $525.00 | $15,750.00 |
| 34 | AC PAVEMENT(PATCH BACK) | 4,524.00 | TON |
128.80
| 32.49 | 96.31 | $180.00 | $17,335.80 |
| 35 | AC PAVEMENT(DRIVEWAYS) | 25.00 | TON |
6.40
| 4.00 | 2.40 | $700.00 | $1,680.00 |
| 47 | PCC CURB, TYPE A1-VAR | 876.00 | LF |
225.00
| 119.00 | 106.00 | $40.00 | $4,240.00 |
| 49 | PCC CURB & GUTTER, TYPE A2-8 | 2,067.00 | LF |
462.50
| 348.90 | 113.60 | $44.00 | $4,998.40 |
| 57 | PCC WALK & DRIVEWAYS, 4" THICK | 38,431.00 | SF |
17,182.71
| 1,074.00 | 16,108.71 | $8.50 | $136,924.04 |
| 58 | PCC CURB RAMPS | 150.00 | CY |
64.37
| 17.14 | 47.23 | $1,200.00 | $56,676.00 |
| 59 | PCC DRIVEWAYS, 6" THICK | 4,910.00 | SF |
1,643.00
| 1,000.00 | 643.00 | $13.00 | $8,359.00 |
| 60 | DETECTABLE WARNING SURFACE | 960.00 | SF |
252.00
| 72.00 | 180.00 | $60.00 | $10,800.00 |
| 62 | CROSS GUTTER (MOD) | 7.00 | CY |
2.28
| 0.00 | 2.28 | $1,200.00 | $2,736.00 |
| 72 | 2" CONDUIT (SCH 80 PVC) | 3,735.00 | LF |
1,814.00
| 1,004.00 | 810.00 | $70.00 | $56,700.00 |
| 73 | 3" CONDUIT (SCH 80 PVC) | 4,215.00 | LF |
1,893.00
| 596.00 | 1,297.00 | $100.00 | $129,700.00 |
| 155 | TYPE 19 STANDARD FOUNDATION | 2.00 | EA |
1.00
| 0.00 | 1.00 | $7,600.00 | $7,600.00 |
| 202 | FLASHING ARROW SIGN | 2.00 | EA |
2.00
| 1.00 | 1.00 | $30,000.00 | $30,000.00 |
| 203 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
2.00
| 1.00 | 1.00 | $60,000.00 | $60,000.00 |
| 206 | IRRIGATION SYSTEM | 1.00 | LS |
0.075
| 0.00 | 0.075 | $1,300,000.00 | $97,500.00 |
| 228 | PCC PAVEMENT (HIGH EARLY STRENGTH) | 456.00 | CY |
97.66
| 31.48 | 66.18 | $535.00 | $35,406.30 |
| 246 | COMPOSITE TYPE 2 PULL BOX INCL COVER | 27.00 | EA |
12.00
| 8.00 | 4.00 | $2,200.00 | $8,800.00 |
| 247 | COMPOSITE TYPE 3 PULL BOX INCL COVER | 71.00 | EA |
24.00
| 5.00 | 19.00 | $2,650.00 | $50,350.00 |
| 261 | 2 INCH DIAMETER NON-METALLIC PVC SCHEDULE 80 BRANCH CONDUIT, FITTINGS AND SUPPORTS | 5,124.00 | LF |
1,756.00
| 741.00 | 1,015.00 | $65.00 | $65,975.00 |
| 264 | SAWCUT AND REMOVE EXISTING ASPHALT CONCRETE (AC) | 4,063.00 | LF |
500.00
| 0.00 | 500.00 | $10.00 | $5,000.00 |
| 265 | UNCLASSIFIED EXCAVATION (TRENCH) | 591.00 | CY |
27.00
| 0.00 | 27.00 | $185.00 | $4,995.00 |
| S-1 | TEMPORARY TRAFFIC SIGNAL POLES | | T&M |
15,531.83
| 0.00 | 15,531.83 | $1.00 | $15,531.83 |
| S-3 | FURNISH & INSTALL CATCH BASIN GRATE | | EA |
32.00
| 0.00 | 32.00 | $1,811.25 | $57,960.00 |
|