| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 2.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 6 | MOBILIZATION | 1.00 | LS |
0.25
| 0.00 | 0.25 | $101,000.00 | $25,250.00 |
| 7 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.50
| 0.25 | 0.25 | $1,500.00 | $375.00 |
| 18 | 3" CONDUIT (SCH 80 PVC) | 460.00 | LF |
337.00
| 0.00 | 337.00 | $200.00 | $67,400.00 |
| 80 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.15 | 0.15 | $33,600.00 | $5,040.00 |