| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.80 | 0.20 | $365,000.00 | $73,000.00 |
| 5 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.95
| 0.85 | 0.10 | $30,000.00 | $3,000.00 |
| 31 | CONSTRUCTION SCHEDULE (UPDATE) (2025) (STIPULATED UNIT PRICE OF $500/MTH) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 32 | IMPLEMENTATION OF BMPS (2025) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $20,000.00 | $20,000.00 |
| 33 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2025) | 1.00 | LS |
1.00
| 0.75 | 0.25 | $85,000.00 | $21,250.00 |
| 34 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN (2025) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $10,000.00 | $10,000.00 |
| 35 | OFFICE FACILITIES (2025) | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $12,000.00 | $12,000.00 |
| 36 | CLEARING AND GRUBBING (2025) | 34.00 | AC |
34.00
| 28.00 | 6.00 | $5,000.00 | $30,000.00 |
| 37 | WATER TRUCKS (2025) | 100.00 | DAYS |
73.00
| 31.00 | 42.00 | $1,200.00 | $50,400.00 |
| 38 | MOBILIZATION (2025) | 1.00 | LS |
0.95
| 0.75 | 0.20 | $200,000.00 | $40,000.00 |
| 40 | MAINTENANCE OF EXCLUSIONARY FENCE (2025) | 9,100.00 | LF |
9,100.00
| 2,000.00 | 7,100.00 | $2.50 | $17,750.00 |
| 42 | SEPARATION OF ORGANIC MATERIAL AND TRASH (2025) | 1,400.00 | TON |
7.77
| 0.00 | 7.77 | $10.00 | $77.70 |
| 45 | TRANSPORTATION AND DISPOSAL OF SEDIMENT TO [SHELDON] (2025) | 120,000.00 | TON |
69,263.27
| 0.00 | 69,263.27 | $9.70 | $671,853.72 |
| 46 | RIPRAP (CLASS V) (2025) | 150.00 | CY |
150.00
| 0.00 | 150.00 | $170.00 | $25,500.00 |
| 47 | PORTABLE SCALES (2025) | 100.00 | DAYS |
60.00
| 18.00 | 42.00 | $1,000.00 | $42,000.00 |
| 48 | RESERVOIR EXCAVATION (2025) | 135,000.00 | TON |
69,263.27
| 0.00 | 69,263.27 | $4.00 | $277,053.08 |
| 49 | STREET SWEEPING (2025) | 100.00 | DAYS |
61.50
| 13.00 | 48.50 | $2,800.00 | $135,800.00 |
| 51 | MAINTENANCE OF TIRE WASH (2025) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $8,000.00 | $8,000.00 |
|