| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | MOBILIZATION | 1.00 | LS |
0.95
| 0.50 | 0.45 | $50,000.00 | $22,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.75
| 0.50 | 0.25 | $25,000.00 | $6,250.00 |
| 6 | OFFICE FACILITIES | 4.00 | MTH |
3.00
| 2.00 | 1.00 | $10,000.00 | $10,000.00 |
| 7 | CONCRETE REMOVAL (REINFORCED) | 40.00 | CY |
20.00
| 5.75 | 14.25 | $4,700.00 | $66,975.00 |
| 9 | BAR REINFORCING STEEL | 20,484.00 | LB |
4,100.00
| 1,502.20 | 2,597.80 | $1.50 | $3,896.70 |
| 10 | TEMPORARY FALSEWORK | 1.00 | LS |
0.60
| 0.20 | 0.40 | $340,000.00 | $136,000.00 |
| 11 | DRILL AND BOND DOWEL | 424.00 | LF |
217.00
| 77.00 | 140.00 | $70.00 | $9,800.00 |
| 12 | DRILL AND BOND DOWEL (OVERHEAD) | 329.00 | LF |
221.00
| 70.00 | 151.00 | $90.00 | $13,590.00 |
| 13 | TRAFFIC CONTROL | 1.00 | LS |
0.20
| 0.00 | 0.20 | $28,522.00 | $5,704.40 |