Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 9/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 5.00 4.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.65 0.500.15$18,750.00$2,812.50
5IMPLEMENTATION OF BMPS1.00LS 0.65 0.500.15$93,750.00$14,062.50
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.65 0.500.15$37,500.00$5,625.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.70 0.600.10$14,950.00$1,495.00
13STRUCTURAL STEEL7,390.00LB 2,790.00 1,995.00795.00$32.00$25,440.00
14TRAFFIC CONTROL1.00LS 0.50 0.150.35$9,375.00$3,281.25
15OFFICE FACILITIES6.00MTH 3.00 2.500.50$4,375.00$2,187.50
20ELECTRICAL1.00LS 0.60 0.450.15$487,566.00$73,134.90
28PIPE WALL ADAPTER PLATES1.00LS 0.60 0.240.36$26,400.00$9,504.00
S-4SUMP PUMP BREAKER UPGRADE LS 1.00 0.001.00$4,700.00$4,700.00
S-5AXIAL FLOW PUMP ANCHORAGE LS 0.21 0.000.21$38,700.00$8,127.00
S-636IN PIPE ADAPTER PLATE MODIFICATIONS LS 1.00 0.001.00$4,350.00$4,350.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $693,680.35 $538,460.70 $155,219.65
Retained $34,684.02 $26,923.04 $7,760.98
Deducted $0.00 $0.00 $0.00
Due $658,996.33 $511,537.66 $147,458.67



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.