| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
2.00
| 0.00 | 2.00 | $500.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.33
| 0.00 | 0.33 | $66,650.00 | $21,994.50 |
| 5 | OFFICE FACILITIES | 5.00 | MTH |
2.00
| 0.00 | 2.00 | $12,700.00 | $25,400.00 |
| 6 | MOBILIZATION | 1.00 | LS |
0.75
| 0.00 | 0.75 | $193,000.00 | $144,750.00 |
| 7 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| 8 | CONCRETE REMOVAL (NON-REINFORCED) | 164.00 | CY |
108.00
| 0.00 | 108.00 | $259.50 | $28,026.00 |
| 9 | UNCLASSIFIED EXCAVATION | 403.00 | CY |
55.00
| 0.00 | 55.00 | $115.00 | $6,325.00 |
| 10 | UNCLASSIFIED EXCAVATION (CHANNEL) | 7,226.00 | CY |
3,691.00
| 0.00 | 3,691.00 | $27.00 | $99,657.00 |
| 11 | UNCLASSIFIED FILL | 337.00 | CY |
337.00
| 0.00 | 337.00 | $67.00 | $22,579.00 |
| 12 | UNCLASSIFIED FILL (CHANNEL) | 7,472.00 | CY |
2,988.00
| 0.00 | 2,988.00 | $32.00 | $95,616.00 |
| 33 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.40
| 0.00 | 0.40 | $12,420.00 | $4,968.00 |
| 35 | CONST & REMOVE TEMP CHAIN LINK FENCE | 1,230.00 | LF |
615.00
| 0.00 | 615.00 | $16.50 | $10,147.50 |