| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.80
| 0.65 | 0.15 | $18,750.00 | $2,812.50 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.80
| 0.65 | 0.15 | $93,750.00 | $14,062.50 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.80
| 0.65 | 0.15 | $37,500.00 | $5,625.00 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.80
| 0.70 | 0.10 | $14,950.00 | $1,495.00 |
| 11 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $68,750.00 | $13,750.00 |
| 12 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 42.00 | LF |
13.00
| 10.00 | 3.00 | $81.00 | $243.00 |
| 13 | STRUCTURAL STEEL | 7,390.00 | LB |
7,390.00
| 2,790.00 | 4,600.00 | $32.00 | $147,200.00 |
| 14 | TRAFFIC CONTROL | 1.00 | LS |
0.80
| 0.50 | 0.30 | $9,375.00 | $2,812.50 |
| 15 | OFFICE FACILITIES | 6.00 | MTH |
4.00
| 3.00 | 1.00 | $4,375.00 | $4,375.00 |
| 18 | FIBERGLASS REINFORCED POLYMER HANDRAIL | 130.00 | LF |
53.22
| 38.00 | 15.22 | $250.00 | $3,805.00 |
| 24 | AXIAL FLOW PUMPS | 1.00 | LS |
0.65
| 0.00 | 0.65 | $1,908,750.00 | $1,240,687.50 |
| 29 | CARBON FIBER PIPE REHABILITATION | 1.00 | LS |
0.39
| 0.00 | 0.39 | $729,100.00 | $284,349.00 |
| 30 | FIBERGLASS REINFORCED POLYMER GRATING | 336.00 | SF |
313.53
| 114.00 | 199.53 | $80.00 | $15,962.40 |
| S-8 | CONDUIT ADJUSTMENT PER RFI NO. 30 | | LS |
1.00
| 0.00 | 1.00 | $5,500.00 | $5,500.00 |