Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 10/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 0.80 0.650.15$18,750.00$2,812.50
5IMPLEMENTATION OF BMPS1.00LS 0.80 0.650.15$93,750.00$14,062.50
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.80 0.650.15$37,500.00$5,625.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.80 0.700.10$14,950.00$1,495.00
11MOBILIZATION1.00LS 0.95 0.750.20$68,750.00$13,750.00
12DRILL AND BOND DOWEL (EPOXY CARTRIDGE)42.00LF 13.00 10.003.00$81.00$243.00
13STRUCTURAL STEEL7,390.00LB 7,390.00 2,790.004,600.00$32.00$147,200.00
14TRAFFIC CONTROL1.00LS 0.80 0.500.30$9,375.00$2,812.50
15OFFICE FACILITIES6.00MTH 4.00 3.001.00$4,375.00$4,375.00
18FIBERGLASS REINFORCED POLYMER HANDRAIL130.00LF 53.22 38.0015.22$250.00$3,805.00
24AXIAL FLOW PUMPS1.00LS 0.65 0.000.65$1,908,750.00$1,240,687.50
29CARBON FIBER PIPE REHABILITATION1.00LS 0.39 0.000.39$729,100.00$284,349.00
30FIBERGLASS REINFORCED POLYMER GRATING336.00SF 313.53 114.00199.53$80.00$15,962.40
S-8CONDUIT ADJUSTMENT PER RFI NO. 30 LS 1.00 0.001.00$5,500.00$5,500.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,436,359.75 $693,680.35 $1,742,679.40
Retained $121,817.99 $34,684.02 $87,133.97
Deducted $0.00 $0.00 $0.00
Due $2,314,541.76 $658,996.33 $1,655,545.43