| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 12.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.24
| 0.16 | 0.08 | $25,000.00 | $2,000.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.24
| 0.16 | 0.08 | $45,000.00 | $3,600.00 |
| 12 | OFFICE FACILITIES | 12.00 | MTH |
3.00
| 2.00 | 1.00 | $3,000.00 | $3,000.00 |
| 18 | UNCLASSIFIED EXCAVATION | 3,925.00 | CY |
868.83
| 688.83 | 180.00 | $135.00 | $24,300.00 |
| 19 | CRUSHED MISCELLANEOUS BASE | 2,770.00 | CY |
688.22
| 305.42 | 382.80 | $110.00 | $42,108.00 |
| 28 | PCC CURB & GUTTER, TYPE A2-6 | 4,853.00 | LF |
3,152.00
| 3,130.00 | 22.00 | $35.00 | $770.00 |
| 32 | PCC WALK, 4" THICK | 52,563.00 | SF |
17,051.00
| 0.00 | 17,051.00 | $8.00 | $136,408.00 |
| 33 | PCC CURB RAMPS | 54.00 | CY |
2.30
| 0.00 | 2.30 | $680.00 | $1,564.00 |
| 35 | PCC DRIVEWAYS, 6" THICK | 1,410.00 | SF |
271.00
| 0.00 | 271.00 | $16.00 | $4,336.00 |
| 36 | DETECTABLE WARNING SURFACE | 205.00 | SF |
15.00
| 0.00 | 15.00 | $45.00 | $675.00 |
| 37 | WATERMETER VAULT | 4.00 | EA |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 38 | 1-1/2" CONDUIT (SCH 80 PVC) | 498.00 | LF |
115.00
| 0.00 | 115.00 | $31.00 | $3,565.00 |
| 42 | 3" CONDUIT (SCH 80 PVC) | 15,544.00 | LF |
3,467.00
| 1,735.00 | 1,732.00 | $45.00 | $77,940.00 |
| 107 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.20 | 0.10 | $317,968.85 | $31,796.89 |
| 109 | IRRIGATION SYSTEM | 1.00 | LS |
0.20
| 0.10 | 0.10 | $485,000.00 | $48,500.00 |
| 152 | SERVICE CONNECTION (SCE) | 8.00 | EA |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 154 | PULL BOX TYPE 2 WITH COVER | 125.00 | EA |
24.00
| 8.00 | 16.00 | $750.00 | $12,000.00 |
| 155 | PULL BOX TYPE 3 WITH COVER | 13.00 | EA |
3.00
| 0.00 | 3.00 | $1,300.00 | $3,900.00 |
| 158 | CONCRETE PEDESTRIAN LIGHT FOUNDATION | 74.00 | EA |
23.00
| 0.00 | 23.00 | $1,550.00 | $35,650.00 |
|