| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 12.00 | MTH |
12.00
| 11.00 | 1.00 | $500.00 | $500.00 |
| 10 | EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $45,000) | 45,000.00 | AL |
2,400.00
| 0.00 | 2,400.00 | $1.00 | $2,400.00 |
| 19 | UNCLASSIFIED EXCAVATION | 8,399.00 | CY |
7,758.00
| 7,735.00 | 23.00 | $165.00 | $3,795.00 |
| 20 | CRUSHED MISCELLANEOUS BASE | 6,963.00 | CY |
5,844.00
| 5,832.00 | 12.00 | $85.00 | $1,020.00 |
| 27 | RECONSTRUCT MANHOLE | 10.00 | EA |
1.00
| 0.00 | 1.00 | $4,300.00 | $4,300.00 |
| 28 | DOUBLE ADJUST MANHOLE | 47.00 | EA |
26.00
| 0.00 | 26.00 | $1,200.00 | $31,200.00 |
| 35 | PCC WALK & DRIVEWAYS, 4" THICK | 42,626.00 | SF |
40,723.00
| 39,800.00 | 923.00 | $14.00 | $12,922.00 |
| 41 | NO. 6 PULL BOX INCL PCC COVER | 6.00 | EA |
1.00
| 0.00 | 1.00 | $1,400.00 | $1,400.00 |
| 47 | 2" CONDUIT (SCH 80 PVC) | 101.00 | LF |
101.00
| 60.00 | 41.00 | $117.00 | $4,797.00 |