| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 3 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.94
| 0.92 | 0.02 | $10,000.00 | $200.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.94
| 0.92 | 0.02 | $25,000.00 | $500.00 |
| 11 | CRUSHED MISCELLANEOUS BASE | 54.00 | CY |
54.00
| 53.63 | 0.37 | $100.00 | $37.00 |
| 13 | STRUCTURE CONCRETE | 13.00 | CY |
13.00
| 10.00 | 3.00 | $700.00 | $2,100.00 |
| 15 | PCC CURB, TYPE A1-6 | 877.00 | LF |
864.50
| 822.50 | 42.00 | $65.00 | $2,730.00 |
| 26 | ELECTRICAL WORK | 1.00 | LS |
0.90
| 0.65 | 0.25 | $350,000.00 | $87,500.00 |
| 28 | PREFAB GUARD BOOTH | 1.00 | LS |
0.60
| 0.30 | 0.30 | $150,000.00 | $45,000.00 |
| 33 | CONCRETE SEATWALL W/ANTI-SKATE BUMPS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $10,000.00 | $1,000.00 |
| 34 | TRASH RECEPTACLE (W/ NEW 6" THICK PERVIOUS CONCRETE PAD) | 10.00 | EA |
10.00
| 7.00 | 3.00 | $2,300.00 | $6,900.00 |
| 35 | BUS SHELTER | 1.00 | LS |
1.00
| 0.91 | 0.09 | $25,000.00 | $2,250.00 |
| 36 | DECORATIVE BOULDERS | 79.00 | EA |
79.00
| 70.00 | 9.00 | $450.00 | $4,050.00 |
| 38 | INTERPRETIVE SIGNAGE | 1.00 | EA |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 40 | IRRIGATION | 1.00 | LS |
1.00
| 0.48 | 0.52 | $80,000.00 | $41,600.00 |
| 41 | FURNISH AND PLANT 24 INCH BOX TREE | 55.00 | EA |
55.00
| 0.00 | 55.00 | $400.00 | $22,000.00 |
| 42 | LANDSCAPING | 1.00 | LS |
1.00
| 0.20 | 0.80 | $80,000.00 | $64,000.00 |
| 43 | PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
0.25
| 0.00 | 0.25 | $15,000.00 | $3,750.00 |
| S-1A | FURNISH & INSTALL (11) 25' LIGHT POLES (NEGOTIATED) | | LS |
1.00
| 0.70 | 0.30 | $128,598.00 | $38,579.40 |
| S-8 | SAW CUT, SLURRY FILL, AND AC TOP (RFI 024) | | LS |
1.00
| 0.50 | 0.50 | $8,867.00 | $4,433.50 |
| S-18 | LAYOUT RECONFIGURATION AT WALK 3 (RFI 032) | | LS |
1.00
| 0.00 | 1.00 | $20,452.00 | $20,452.00 |
| S-19 | ADDITIONAL SOIL WORK | | LS |
1.00
| 0.00 | 1.00 | $5,679.00 | $5,679.00 |
|