Los Angeles County Public Works
Project Management Division III
Progress Payment 6
Project Name: Bridge Preventive Maintenance Program - Group 16 Cities
Contractor: Beador Construction Company, Inc.
2900 Bristol Street, Suite D204
Costa Mesa, CA 92626-5981
Project ID: RDC0015922
Federal Number(s): BPMPL-5953(726)
Original Contract: $2,210,300.00
Awarded: 5/20/2024
Period Ending: 10/29/2025
There is NO item progress this period

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,097,653.91 $2,097,653.91 $0.00
Retained $52,441.69 $104,882.69 ($52,441.00)
Deducted $30,374.43 $30,374.43 $0.00
Due $2,014,837.79 $1,962,396.79 $52,441.00