| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 5 | CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $3,000) | 3,000.00 | AL |
3,000.00
| 2,000.00 | 1,000.00 | $1.00 | $1,000.00 |
| 6 | OFFICE FACILITIES | 6.00 | MTH |
3.00
| 2.00 | 1.00 | $5,333.00 | $5,333.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.75
| 0.20 | 0.55 | $52,000.00 | $28,600.00 |
| 8 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.50 | 0.50 | $8,500.00 | $4,250.00 |
| 12 | UNCLASSIFIED EXCAVATION | 42.00 | CY |
22.00
| 10.00 | 12.00 | $250.00 | $3,000.00 |
| 13 | STRUCTURE EXCAVATION | 27.00 | CY |
24.00
| 0.00 | 24.00 | $300.00 | $7,200.00 |
| 14 | STRUCTURE BACKFILL | 9.00 | CY |
6.00
| 0.00 | 6.00 | $500.00 | $3,000.00 |
| 15 | STRUCTURE CONCRETE | 18.00 | CY |
18.00
| 0.00 | 18.00 | $2,500.00 | $45,000.00 |
| 16 | BAR REINFORCING STEEL | 1,500.00 | LB |
1,500.00
| 0.00 | 1,500.00 | $20.00 | $30,000.00 |
| 17 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.20 | 0.10 | $45,000.00 | $4,500.00 |
| 19 | IRRIGATION SYSTEM | 1.00 | LS |
0.15
| 0.00 | 0.15 | $15,000.00 | $2,250.00 |
| 22 | ELECTRICAL WORK | 1.00 | LS |
0.40
| 0.00 | 0.40 | $12,500.00 | $5,000.00 |
| 33 | COMPOSITE DECK | 1.00 | LS |
0.20
| 0.00 | 0.20 | $189,000.00 | $37,800.00 |
| S-4 | CONCRETE SIDEWALK, SITE 4 (CO #1) | | SF |
350.00
| 0.00 | 350.00 | $13.00 | $4,550.00 |
| S-4A | CONCRETE SIDEWALK, SITE 4 (CO #1A) | | SF |
175.00
| 0.00 | 175.00 | $13.00 | $2,275.00 |
| S-7 | TREE AND STUMP REMOVAL (CO #2) | | LS |
1.00
| 0.00 | 1.00 | $3,857.00 | $3,857.00 |
|