| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 6 | OFFICE FACILITIES | 6.00 | MTH |
4.00
| 3.00 | 1.00 | $5,333.00 | $5,333.00 |
| 7 | MOBILIZATION | 1.00 | LS |
1.00
| 0.75 | 0.25 | $52,000.00 | $13,000.00 |
| 11 | CONCRETE REMOVAL (NON-REINFORCED) | 8.00 | CY |
7.00
| 0.00 | 7.00 | $400.00 | $2,800.00 |
| 12 | UNCLASSIFIED EXCAVATION | 42.00 | CY |
37.00
| 22.00 | 15.00 | $250.00 | $3,750.00 |
| 17 | TRAFFIC CONTROL | 1.00 | LS |
0.40
| 0.30 | 0.10 | $45,000.00 | $4,500.00 |
| 19 | IRRIGATION SYSTEM | 1.00 | LS |
0.30
| 0.15 | 0.15 | $15,000.00 | $2,250.00 |
| 21 | CONCRETE UNIT PAVER | 504.00 | SF |
406.00
| 0.00 | 406.00 | $17.00 | $6,902.00 |
| 24 | TREE PROTECTION FENCING | 1.00 | LS |
0.50
| 0.00 | 0.50 | $4,000.00 | $2,000.00 |
| 27 | CONCRETE HEADER, 6" X 6" | 93.00 | LF |
89.00
| 0.00 | 89.00 | $80.00 | $7,120.00 |
| 33 | COMPOSITE DECK | 1.00 | LS |
0.60
| 0.20 | 0.40 | $189,000.00 | $75,600.00 |
| S-2 | TYPE A3 CURB &GUTTER, SITE 2 (CO #1) | | LF |
42.00
| 0.00 | 42.00 | $54.00 | $2,268.00 |
| S-8 | REMOVAL OF PAVEMENT AND BASE, AND BACKFILL WITH SOIL (CO 3) | | LS |
1.00
| 0.00 | 1.00 | $11,975.00 | $11,975.00 |