| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
4.00
| 2.00 | 2.00 | $500.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.65
| 0.50 | 0.15 | $66,650.00 | $9,997.50 |
| 5 | OFFICE FACILITIES | 5.00 | MTH |
4.00
| 3.00 | 1.00 | $12,700.00 | $12,700.00 |
| 6 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $193,000.00 | $9,650.00 |
| 9 | UNCLASSIFIED EXCAVATION | 403.00 | CY |
241.00
| 55.00 | 186.00 | $115.00 | $21,390.00 |
| 13 | STRUCTURE EXCAVATION | 29.00 | CY |
29.00
| 0.00 | 29.00 | $275.00 | $7,975.00 |
| 17 | CONSTRUCT SHEET PILE WALL | 127.00 | LF |
127.00
| 40.00 | 87.00 | $4,869.00 | $423,603.00 |
| 21 | STAINLESS STEEL COVER PLATE | 2.00 | EA |
2.00
| 0.40 | 1.60 | $12,420.00 | $19,872.00 |