| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.08
| 0.00 | 0.08 | $324,000.00 | $25,920.00 |
| 6 | PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 7 | PREPARATION OF THE NOISE MITIGATION PLAN (STIPULATED PRICE OF $15,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $15,000.00 | $15,000.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
1.00
| 0.00 | 1.00 | $4,000.00 | $4,000.00 |
| 9 | TEMPORARY SOUND BARRIER | 1,000.00 | LF |
720.00
| 0.00 | 720.00 | $65.00 | $46,800.00 |
| 11 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 15 | INSTALLATION OF WILDLIFE EXCLUSIONARY FENCING | 3,500.00 | LF |
1,400.00
| 0.00 | 1,400.00 | $20.00 | $28,000.00 |
| 18 | PREPARATION OF THE FUGITIVE DUST CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
9.00
| 0.00 | 9.00 | $1,800.00 | $16,200.00 |
| 23 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.08
| 0.00 | 0.08 | $34,000.00 | $2,720.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 28 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.15
| 0.00 | 0.15 | $35,000.00 | $5,250.00 |
| 29 | CLEARING AND GRUBBING | 1.00 | LS |
0.18
| 0.00 | 0.18 | $50,000.00 | $9,000.00 |
| 30 | TREE PRUNING ($30,000 ALLOWANCE) | 30,000.00 | AL |
402.50
| 0.00 | 402.50 | $1.00 | $402.50 |
| 31 | REMOVE EXISTING CHAIN LINK FENCE AND PIPE GATE | 266.00 | LF |
266.00
| 0.00 | 266.00 | $20.00 | $5,320.00 |
| 32 | REMOVE EXISTING TREES | 16.00 | EA |
16.00
| 0.00 | 16.00 | $2,000.00 | $32,000.00 |
| 34 | REMOVE EXISTING LONGITUDINAL GUTTER | 77.00 | LF |
30.00
| 0.00 | 30.00 | $40.00 | $1,200.00 |
| 36 | AC PAVEMENT REMOVAL | 27,630.00 | SF |
6,313.00
| 0.00 | 6,313.00 | $0.75 | $4,734.75 |
| 37 | UNCLASSIFIED EXCAVATION | 8,927.00 | CY |
4,400.00
| 0.00 | 4,400.00 | $40.00 | $176,000.00 |
| 80 | CONTROL BUILDING | 1.00 | LS |
0.03
| 0.00 | 0.03 | $700,000.00 | $21,000.00 |
| 82 | ELECTRICAL WORK | 1.00 | LS |
0.03
| 0.00 | 0.03 | $454,000.00 | $13,620.00 |
|