| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.16
| 0.08 | 0.08 | $324,000.00 | $25,920.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
2.00
| 1.00 | 1.00 | $4,000.00 | $4,000.00 |
| 9 | TEMPORARY SOUND BARRIER | 1,000.00 | LF |
860.00
| 720.00 | 140.00 | $65.00 | $9,100.00 |
| 13 | INSTALLATION OF ESA FENCING | 2,000.00 | LF |
360.00
| 0.00 | 360.00 | $8.50 | $3,060.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
30.00
| 9.00 | 21.00 | $1,800.00 | $37,800.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
2.00
| 1.00 | 1.00 | $5,000.00 | $5,000.00 |
| 37 | UNCLASSIFIED EXCAVATION | 8,927.00 | CY |
4,744.00
| 4,400.00 | 344.00 | $40.00 | $13,760.00 |
| 38 | PERMEABLE ZONE MATERIAL | 2,691.00 | CY |
700.00
| 0.00 | 700.00 | $80.00 | $56,000.00 |
| 39 | BUTTRESS FILL | 16,505.00 | CY |
4,374.00
| 0.00 | 4,374.00 | $55.00 | $240,570.00 |
| 58 | DECOMMISSION EXISTING PIEZOMETERS | 3.00 | EA |
3.00
| 0.00 | 3.00 | $9,500.00 | $28,500.00 |
| 74 | SPILLWAY WALL BUTTRESS COMPLETE IN PLACE | 1.00 | LS |
0.05
| 0.00 | 0.05 | $6,000,000.00 | $300,000.00 |