Los Angeles County Public Works
Project Management Division III
Progress Payment 7
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 12/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 8.00 7.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.95 0.900.05$18,750.00$937.50
5IMPLEMENTATION OF BMPS1.00LS 0.95 0.900.05$93,750.00$4,687.50
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.95 0.900.05$37,500.00$1,875.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.95 0.900.05$14,950.00$747.50
14TRAFFIC CONTROL1.00LS 0.95 0.900.05$9,375.00$468.75
15OFFICE FACILITIES6.00MTH 6.00 5.001.00$4,375.00$4,375.00
18FIBERGLASS REINFORCED POLYMER HANDRAIL130.00LF 130.00 110.4019.60$250.00$4,900.00
20ELECTRICAL1.00LS 0.75 0.710.04$487,566.00$19,502.64
27VALVES, PIPES AND FITTINGS1.00LS 0.65 0.520.13$67,550.00$8,781.50
29CARBON FIBER PIPE REHABILITATION1.00LS 0.61 0.390.22$729,100.00$160,402.00
30FIBERGLASS REINFORCED POLYMER GRATING336.00SF 336.00 325.8610.14$80.00$811.20
S-3PLUG TRANSITION STRUCTURE LS 1.00 0.800.20$27,000.00$5,400.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,807,500.70 $3,594,112.11 $213,388.59
Retained $190,375.04 $179,705.61 $10,669.43
Deducted $0.00 $0.00 $0.00
Due $3,617,125.66 $3,414,406.50 $202,719.16



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.