| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
8.00
| 7.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.95
| 0.90 | 0.05 | $18,750.00 | $937.50 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.95
| 0.90 | 0.05 | $93,750.00 | $4,687.50 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.95
| 0.90 | 0.05 | $37,500.00 | $1,875.00 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.95
| 0.90 | 0.05 | $14,950.00 | $747.50 |
| 14 | TRAFFIC CONTROL | 1.00 | LS |
0.95
| 0.90 | 0.05 | $9,375.00 | $468.75 |
| 15 | OFFICE FACILITIES | 6.00 | MTH |
6.00
| 5.00 | 1.00 | $4,375.00 | $4,375.00 |
| 18 | FIBERGLASS REINFORCED POLYMER HANDRAIL | 130.00 | LF |
130.00
| 110.40 | 19.60 | $250.00 | $4,900.00 |
| 20 | ELECTRICAL | 1.00 | LS |
0.75
| 0.71 | 0.04 | $487,566.00 | $19,502.64 |
| 27 | VALVES, PIPES AND FITTINGS | 1.00 | LS |
0.65
| 0.52 | 0.13 | $67,550.00 | $8,781.50 |
| 29 | CARBON FIBER PIPE REHABILITATION | 1.00 | LS |
0.61
| 0.39 | 0.22 | $729,100.00 | $160,402.00 |
| 30 | FIBERGLASS REINFORCED POLYMER GRATING | 336.00 | SF |
336.00
| 325.86 | 10.14 | $80.00 | $811.20 |
| S-3 | PLUG TRANSITION STRUCTURE | | LS |
1.00
| 0.80 | 0.20 | $27,000.00 | $5,400.00 |