| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.30
| 0.25 | 0.05 | $45,000.00 | $2,250.00 |
| 16 | OFFICE FACILITIES | 25.00 | MTH |
5.00
| 4.00 | 1.00 | $15,000.00 | $15,000.00 |
| 17 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $2,600,000.00 | $520,000.00 |
| 18 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.25 | 0.05 | $1,700,000.00 | $85,000.00 |
| 27 | CONCRETE REMOVAL (NON-REINFORCED) | 3,340.00 | CY |
1,123.85
| 951.72 | 172.13 | $240.00 | $41,311.20 |
| 29 | UNCLASSIFIED EXCAVATION | 23,912.00 | CY |
10,523.31
| 10,411.82 | 111.49 | $100.00 | $11,149.00 |
| 31 | CRUSHED MISCELLANEOUS BASE | 4,311.00 | CY |
1,441.45
| 1,429.17 | 12.28 | $235.00 | $2,885.80 |
| 34 | AC PAVEMENT(PATCH BACK) | 4,524.00 | TON |
319.68
| 306.60 | 13.08 | $180.00 | $2,354.40 |
| 58 | PCC CURB RAMPS | 150.00 | CY |
74.72
| 73.86 | 0.86 | $1,200.00 | $1,032.00 |
| 60 | DETECTABLE WARNING SURFACE | 960.00 | SF |
348.00
| 309.00 | 39.00 | $60.00 | $2,340.00 |
| 72 | 2" CONDUIT (SCH 80 PVC) | 3,735.00 | LF |
1,987.00
| 1,846.00 | 141.00 | $70.00 | $9,870.00 |
| 73 | 3" CONDUIT (SCH 80 PVC) | 4,215.00 | LF |
2,887.00
| 2,258.00 | 629.00 | $100.00 | $62,900.00 |
| 145 | TYPE III-BF SERVICE CABINET FOUNDATION | 6.00 | EA |
3.00
| 0.00 | 3.00 | $3,225.00 | $9,675.00 |
| 146 | TYPE III-BF SERVICE CABINET | 2.00 | EA |
2.00
| 0.00 | 2.00 | $8,600.00 | $17,200.00 |
| 205 | LANDSCAPING | 1.00 | LS |
0.03
| 0.00 | 0.03 | $575,000.00 | $17,250.00 |
| 206 | IRRIGATION SYSTEM | 1.00 | LS |
0.40
| 0.30 | 0.10 | $1,300,000.00 | $130,000.00 |
| 246 | COMPOSITE TYPE 2 PULL BOX INCL COVER | 27.00 | EA |
20.00
| 18.00 | 2.00 | $2,200.00 | $4,400.00 |
| 247 | COMPOSITE TYPE 3 PULL BOX INCL COVER | 71.00 | EA |
35.00
| 29.00 | 6.00 | $2,650.00 | $15,900.00 |
| 259 | EDISON 3 INCH NON-METALLIC PVC SCHEDULE 80 WITH PULL TAPE, FITTINGS AND SUPPORTS | 821.00 | LF |
145.00
| 0.00 | 145.00 | $100.00 | $14,500.00 |
| 260 | PULL BOX, 17 INCH BY 30 INCH BY 12 INCH | 6.00 | EA |
2.00
| 0.00 | 2.00 | $575.00 | $1,150.00 |
| 267 | RIVER ROCK PAVING, 4" THICK | 42,485.00 | SF |
7,090.00
| 0.00 | 7,090.00 | $17.00 | $120,530.00 |
| S-8 | REVISE TRAFFIC CONTROL PLANS | | LS |
0.50
| 0.00 | 0.50 | $13,663.00 | $6,831.50 |
| S-11 | REMOVE AND REPLACE MEDIAN NOSES | | T&M |
10,721.15
| 0.00 | 10,721.15 | $1.00 | $10,721.15 |
|