| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 9.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.10
| 0.00 | 0.10 | $8,000.00 | $800.00 |
| 5 | PREPARATION OF THE NOISE MITIGATION PLAN (STIPULATED LS UNIT PRICE $10,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| 8 | IMPLEMENTATION OF THE NOISE MITIGATION PLAN | 1.00 | LS |
0.10
| 0.00 | 0.10 | $16,500.00 | $1,650.00 |
| 9 | TEMPORARY SOUND WALLS | 1.00 | LS |
0.25
| 0.00 | 0.25 | $93,500.00 | $23,375.00 |
| 10 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.10
| 0.00 | 0.10 | $35,000.00 | $3,500.00 |
| 11 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.25
| 0.00 | 0.25 | $2,000.00 | $500.00 |
| 12 | PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $5000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 15 | OFFICE FACILITIES | 10.00 | MTH |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 41 | REMOVE AND DISPOSE EXISTING FENCING | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,980.00 | $2,980.00 |
| 43 | MASONRY BLOCK WALL | 804.00 | LF |
41.00
| 0.00 | 41.00 | $303.00 | $12,423.00 |
| 44 | REMOVE AND DISPOSE EXISTING BLOCK WALL | 1,250.00 | SF |
1,250.00
| 0.00 | 1,250.00 | $17.00 | $21,250.00 |
| 56 | UNCLASSIFIED EXCAVATION (RETENTION BASIN) | 226.00 | CY |
208.00
| 0.00 | 208.00 | $110.00 | $22,880.00 |
| 76 | TEMPORARY POWER (WELL 4-91) | 6.00 | MTH |
0.60
| 0.00 | 0.60 | $21,560.00 | $12,936.00 |
| S-1 | MOTOR CONTROL CENTER W/ VFD CONTROLS | | LS |
1.00
| 0.00 | 1.00 | $32,445.00 | $32,445.00 |