Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Avenue J-12 and 50th Street West Site Improvements Well 4-91
Contractor: Environmental Construction, Inc.
21550 Oxnard Street, Suite 1060
Woodland Hills, CA 91367
Project ID: WWD4004057
Federal Number(s): XP-99T25001
Original Contract: $4,587,457.00
Awarded: 12/30/2024
Period Ending: 12/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)9.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.10 0.000.10$8,000.00$800.00
5PREPARATION OF THE NOISE MITIGATION PLAN (STIPULATED LS UNIT PRICE $10,000)1.00LS 1.00 0.001.00$10,000.00$10,000.00
8IMPLEMENTATION OF THE NOISE MITIGATION PLAN1.00LS 0.10 0.000.10$16,500.00$1,650.00
9TEMPORARY SOUND WALLS1.00LS 0.25 0.000.25$93,500.00$23,375.00
10IMPLEMENTATION OF BMPS1.00LS 0.10 0.000.10$35,000.00$3,500.00
11SHORING OF OPEN EXCAVATIONS1.00LS 0.25 0.000.25$2,000.00$500.00
12PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $5000)1.00LS 1.00 0.001.00$5,000.00$5,000.00
15OFFICE FACILITIES10.00MTH 1.00 0.001.00$3,000.00$3,000.00
41REMOVE AND DISPOSE EXISTING FENCING1.00LS 1.00 0.001.00$2,980.00$2,980.00
43MASONRY BLOCK WALL804.00LF 41.00 0.0041.00$303.00$12,423.00
44REMOVE AND DISPOSE EXISTING BLOCK WALL1,250.00SF 1,250.00 0.001,250.00$17.00$21,250.00
56UNCLASSIFIED EXCAVATION (RETENTION BASIN)226.00CY 208.00 0.00208.00$110.00$22,880.00
76TEMPORARY POWER (WELL 4-91)6.00MTH 0.60 0.000.60$21,560.00$12,936.00
S-1MOTOR CONTROL CENTER W/ VFD CONTROLS LS 1.00 0.001.00$32,445.00$32,445.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $155,739.00 $0.00 $155,739.00
Retained* $7,786.95 $0.00 $7,786.95
Deducted $0.00 $0.00 $0.00
Due $147,952.05 $0.00 $147,952.05



*This project has an escrow account.