Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: Metro Gold Line Eastside Access Phase II Calvary Cemetery Pedestrian Path
Contractor: Los Angeles Engineering, Inc.
633 North Barranca Avenue
Covina, CA 91723
Project ID: RDC0016013
Federal Number(s): None
Original Contract: $8,533,000.00
Awarded: 4/4/2025
Period Ending: 12/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)12.00MTH 5.00 4.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.40 0.320.08$25,000.00$2,000.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.40 0.320.08$45,000.00$3,600.00
12OFFICE FACILITIES12.00MTH 5.00 4.001.00$3,000.00$3,000.00
13MOBILIZATION1.00LS 0.75 0.500.25$827,000.00$206,750.00
29PCC CURB & GUTTER, TYPE A2-85,084.00LF 2,940.00 0.002,940.00$40.00$117,600.00
423" CONDUIT (SCH 80 PVC)15,544.00LF 4,601.00 3,587.001,014.00$45.00$45,630.00
109IRRIGATION SYSTEM1.00LS 0.66 0.330.33$485,000.00$160,050.00
125RUBBER WALKWAY47,489.00SF 14,150.00 0.0014,150.00$33.00$466,950.00
137REWIRE INTERSECTION1.00LS 0.50 0.330.17$27,000.00$4,590.00
144PROTECT EXISTING INTERCONNECT CABLE1.00LS 1.00 0.001.00$700.00$700.00
160RELOCATE PEDESTRIAN PUSH BUTTON INCLUDING WIRING1.00EA 1.00 0.001.00$450.00$450.00
168REMOVE PED PUSH BUTTON POST FOUNDATION1.00EA 1.00 0.001.00$110.00$110.00
S-1SCE ENCASEMENT CONFLICT LS 1.00 0.001.00$5,764.02$5,764.02
S-2PCC CURB AND GUTTER, TYPE A2-VAR LF 274.00 0.00274.00$120.00$32,880.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,137,143.92 $2,086,569.90 $1,050,574.02
Retained* $156,857.20 $104,328.50 $52,528.70
Deducted $0.00 $0.00 $0.00
Due $2,980,286.72 $1,982,241.40 $998,045.32



*This project has an escrow account.

Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.