| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $50,000.00 | $2,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 0.75 | 0.25 | $25,000.00 | $6,250.00 |
| 6 | OFFICE FACILITIES | 4.00 | MTH |
4.00
| 3.00 | 1.00 | $10,000.00 | $10,000.00 |
| 7 | CONCRETE REMOVAL (REINFORCED) | 40.00 | CY |
32.50
| 20.00 | 12.50 | $4,700.00 | $58,750.00 |
| 8 | STRUCTURE CONCRETE | 40.00 | CY |
32.50
| 0.00 | 32.50 | $5,500.00 | $178,750.00 |
| 9 | BAR REINFORCING STEEL | 20,484.00 | LB |
15,570.00
| 4,100.00 | 11,470.00 | $1.50 | $17,205.00 |
| 10 | TEMPORARY FALSEWORK | 1.00 | LS |
0.90
| 0.60 | 0.30 | $340,000.00 | $102,000.00 |
| 11 | DRILL AND BOND DOWEL | 424.00 | LF |
368.00
| 217.00 | 151.00 | $70.00 | $10,570.00 |
| 12 | DRILL AND BOND DOWEL (OVERHEAD) | 329.00 | LF |
329.00
| 221.00 | 108.00 | $90.00 | $9,720.00 |
| 13 | TRAFFIC CONTROL | 1.00 | LS |
0.75
| 0.20 | 0.55 | $28,522.00 | $15,687.10 |