| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 6 | OFFICE FACILITIES | 4.00 | MTH |
5.00
| 4.00 | 1.00 | $10,000.00 | $10,000.00 |
| 7 | CONCRETE REMOVAL (REINFORCED) | 40.00 | CY |
38.60
| 32.50 | 6.10 | $4,700.00 | $28,670.00 |
| 8 | STRUCTURE CONCRETE | 40.00 | CY |
38.60
| 32.50 | 6.10 | $5,500.00 | $33,550.00 |
| 9 | BAR REINFORCING STEEL | 20,484.00 | LB |
16,800.00
| 15,570.00 | 1,230.00 | $1.50 | $1,845.00 |
| 10 | TEMPORARY FALSEWORK | 1.00 | LS |
1.00
| 0.90 | 0.10 | $340,000.00 | $34,000.00 |
| 11 | DRILL AND BOND DOWEL | 424.00 | LF |
420.00
| 368.00 | 52.00 | $70.00 | $3,640.00 |
| 12 | DRILL AND BOND DOWEL (OVERHEAD) | 329.00 | LF |
854.00
| 329.00 | 525.00 | $90.00 | $47,250.00 |
| 13 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.75 | 0.25 | $28,522.00 | $7,130.50 |