Los Angeles County Public Works
Project Management Division III
As-Built 5
Project Name: Bradbury Channel Soffit Repair Phase II
Contractor: LBI
510 E. Jamie Ave
La Habra, CA 90631-6842
Project ID: FCC0001404
Federal Number(s): None
Original Contract: $986,038.00
Awarded: 3/12/2025
Period Ending: 11/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000)1.00LS 1.00 1.000.00$2,000.00$0.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)3.00MTH 3.00 3.000.00$500.00$0.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
4MOBILIZATION1.00LS 1.00 1.000.00$50,000.00$0.00
5IMPLEMENTATION OF BMPS1.00LS 1.00 1.000.00$25,000.00$0.00
6OFFICE FACILITIES4.00MTH 5.00 4.001.00$10,000.00$10,000.00
7CONCRETE REMOVAL (REINFORCED)40.00CY 38.60 32.506.10$4,700.00$28,670.00
8STRUCTURE CONCRETE40.00CY 38.60 32.506.10$5,500.00$33,550.00
9BAR REINFORCING STEEL20,484.00LB 16,800.00 15,570.001,230.00$1.50$1,845.00
10TEMPORARY FALSEWORK1.00LS 1.00 0.900.10$340,000.00$34,000.00
11DRILL AND BOND DOWEL424.00LF 420.00 368.0052.00$70.00$3,640.00
12DRILL AND BOND DOWEL (OVERHEAD)329.00LF 854.00 329.00525.00$90.00$47,250.00
13TRAFFIC CONTROL1.00LS 1.00 0.750.25$28,522.00$7,130.50

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,023,202.00 $856,116.50 $167,085.50
Retained $51,160.10 $42,805.83 $8,354.27
Deducted $0.00 $0.00 $0.00
Due $972,041.90 $813,310.67 $158,731.23



*The term "As-Built" used by the Department of Public Works in combination with the Engineer's Monthly Estimate process indicates that the project has been field accepted and that the pay quantities and deductions as detailed above are FINAL. Unless a certified letter is received by this office within 14 calendar days disputing the amounts shown, an acceptance letter will be filed with the Board of Supervisors authorizing the release of retention.

Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.