| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 3 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.98
| 0.94 | 0.04 | $10,000.00 | $400.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.98
| 0.94 | 0.04 | $25,000.00 | $1,000.00 |
| 15 | PCC CURB, TYPE A1-6 | 877.00 | LF |
877.00
| 864.50 | 12.50 | $65.00 | $812.50 |
| 17 | PERVIOUS CONCRETE, 6" THICK | 2,216.00 | SF |
2,216.00
| 2,210.537 | 5.463 | $30.50 | $166.62 |
| 26 | ELECTRICAL WORK | 1.00 | LS |
0.98
| 0.90 | 0.08 | $350,000.00 | $28,000.00 |
| 28 | PREFAB GUARD BOOTH | 1.00 | LS |
1.00
| 0.60 | 0.40 | $150,000.00 | $60,000.00 |
| 43 | PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
0.75
| 0.25 | 0.50 | $15,000.00 | $7,500.00 |
| S-12 | TEMPORARY LIGHTING (COP12R1) | | LS |
0.90
| 0.80 | 0.10 | $19,709.00 | $1,970.90 |
| S-13 | TEMPORARY FENCE AND ADDITIONAL MOBILIZATION (COP13) | | LS |
0.90
| 0.75 | 0.15 | $29,573.00 | $4,435.95 |