Project Name: Devil's Gate Reservoir Annual Cleanout '24 & '25
Contractor: AMES CONSTRUCTION INC
2500 County Road 42 West
Burnsville , MN 55337
Project ID: WRDM000063
Federal Number(s): None
Original Contract: $9,145,350.00
Awarded: 4/16/2024
Period Ending: 10/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1PREPARATION OF THE SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 1.000.00$5,000.00$0.00
2PREPARATION OF THE FUGITIVE DUST CONTROL PLAN (STIPULATED UNIT PRICE OF $1,500/YEAR)2.00YR 2.00 2.000.00$1,500.00$0.00
3PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
4TRAFFIC CONTROL1.00LS 1.00 1.000.00$365,000.00$0.00
5IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.950.05$30,000.00$1,500.00
6CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $10,000)10,000.00AL 460.00 460.000.00$1.00$0.00
7CONSTRUCTION SCHEDULE (BASELINE) (2024) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
8CONSTRUCTION SCHEDULE (UPDATE) (2024) (STIPULATED UNIT PRICE OF $500/MTH)5.00MTH 3.00 3.000.00$500.00$0.00
9IMPLEMENTATION OF BMPS (2024)5.00MTH 3.00 3.000.00$20,000.00$0.00
10IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2024)1.00LS 1.00 1.000.00$400,000.00$0.00
11IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN (2024)5.00MTH 3.00 3.000.00$10,000.00$0.00
12OFFICE FACILITIES (2024)5.00MTH 4.00 4.000.00$12,000.00$0.00
13CLEARING AND GRUBBING (2024)34.00AC 34.00 34.000.00$10,000.00$0.00
14WATER TRUCKS (2024)100.00DAYS 75.00 75.000.00$1,100.00$0.00
15MOBILIZATION (2024)1.00LS 1.00 1.000.00$605,000.00$0.00
16INSTALLATION OF EXCLUSIONARY FENCE (2024)9,100.00LF 9,100.00 9,100.000.00$10.00$0.00
17MAINTENANCE OF EXCLUSIONARY FENCE (2024)9,100.00LF 9,100.00 9,100.000.00$2.50$0.00
18REMOVAL OF EXCLUSIONARY FENCE (2024)1.00LS 1.00 1.000.00$21,000.00$0.00
19SEPARATION OF ORGANIC MATERIAL AND TRASH (2024)1,400.00TON 19.46 19.460.00$10.00$0.00
20TRANSPORTATION AND DISPOSAL OF SEDIMENT AT [KINCAID] (2024)15,000.00TON 0.00 0.000.00$10.50$0.00
21TRANSPORTATION AND DISPOSAL OF ORGANIC MATERIAL AT [SCHOLL] (2024)1,400.00TON 0.00 0.000.00$30.00$0.00
22TRANSPORTATION AND DISPOSAL OF SEDIMENT TO [SHELDON] (2024)187,500.00TON 52,079.06 52,079.060.00$9.60$0.00
23RIPRAP (CLASS V) (2024)150.00CY 798.61 798.610.00$170.00$0.00
24PORTABLE SCALES (2024)100.00DAYS 70.00 70.000.00$1,500.00$0.00
25RESERVOIR EXCAVATION (2024)202,500.00TON 86,268.06 86,268.060.00$4.50$0.00
26STREET SWEEPING (2024)100.00DAYS 53.00 53.000.00$2,800.00$0.00
27INSTALLATION OF TIRE WASH (2024)2.00EA 2.00 2.000.00$60,000.00$0.00
28MAINTENANCE OF TIRE WASH (2024)5.00MTH 2.00 2.000.00$8,000.00$0.00
29REMOVAL OF TIRE WASH (2024)2.00EA 2.00 2.000.00$5,000.00$0.00
30CONSTRUCTION SCHEDULE (BASELINE) (2025) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
31CONSTRUCTION SCHEDULE (UPDATE) (2025) (STIPULATED UNIT PRICE OF $500/MTH)5.00MTH 3.00 2.001.00$500.00$500.00
32IMPLEMENTATION OF BMPS (2025)5.00MTH 2.50 2.000.50$20,000.00$10,000.00
33IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2025)1.00LS 1.00 1.000.00$85,000.00$0.00
34IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN (2025)5.00MTH 2.50 2.000.50$10,000.00$5,000.00
35OFFICE FACILITIES (2025)6.00MTH 3.00 2.001.00$12,000.00$12,000.00
36CLEARING AND GRUBBING (2025)34.00AC 34.00 34.000.00$5,000.00$0.00
37WATER TRUCKS (2025)100.00DAYS 79.00 73.006.00$1,200.00$7,200.00
38MOBILIZATION (2025)1.00LS 1.00 0.950.05$200,000.00$10,000.00
39INSTALLATION OF EXCLUSIONARY FENCE (2025)9,100.00LF 9,100.00 9,100.000.00$6.00$0.00
40MAINTENANCE OF EXCLUSIONARY FENCE (2025)9,100.00LF 9,100.00 9,100.000.00$2.50$0.00
41REMOVAL OF EXCLUSIONARY FENCE (2025)1.00LS 1.00 0.001.00$21,000.00$21,000.00
42SEPARATION OF ORGANIC MATERIAL AND TRASH (2025)1,400.00TON 7.77 7.770.00$10.00$0.00
43TRANSPORTATION AND DISPOSAL OF SEDIMENT AT [KINCAID] (2025)15,000.00TON 0.00 0.000.00$10.60$0.00
44TRANSPORTATION AND DISPOSAL OF ORGANIC MATERIAL AT [SCHOLL] (2025)1,400.00TON 0.00 0.000.00$30.00$0.00
45TRANSPORTATION AND DISPOSAL OF SEDIMENT TO [SHELDON] (2025)120,000.00TON 69,263.27 69,263.270.00$9.70$0.00
46RIPRAP (CLASS V) (2025)150.00CY 150.00 150.000.00$170.00$0.00
47PORTABLE SCALES (2025)100.00DAYS 70.00 60.0010.00$1,000.00$10,000.00
48RESERVOIR EXCAVATION (2025)135,000.00TON 69,263.27 69,263.270.00$4.00$0.00
49STREET SWEEPING (2025)100.00DAYS 70.50 61.509.00$2,800.00$25,200.00
50INSTALLATION OF TIRE WASH (2025)2.00EA 2.00 2.000.00$50,000.00$0.00
51MAINTENANCE OF TIRE WASH (2025)5.00MTH 1.00 1.000.00$8,000.00$0.00
52REMOVAL OF TIRE WASH (2025)2.00EA 2.00 0.002.00$5,000.00$10,000.00
S-1EXTEND NTP PART 1 DURATION WD 9.00 9.000.00$0.00$0.00
S-2LOCATE FIELD OFFICE WITHIN PROJECT SITE LS 1.00 1.000.00$0.00$0.00
S-32024 TRAFFIC CONTROL AT SHELDON PIT DAYS 16.00 16.000.00$1,897.09$0.00
S-4SOIL TESTING FOR VULCAN LS 1.00 1.000.00$21,387.66$0.00
S-52024 SIDE SLOPE REPAIR LS 1.00 1.000.00$30,327.29$0.00
S-6ENTRANCE GATE AND FENCE REPAIR LS 1.00 1.000.00$6,468.00$0.00
S-7QUANTITY DISCREPANCY ADJUSTMENT 2024 LS 1.00 1.000.00$50,000.00$0.00
S-8FEMA CONTRACT AMENDMENT (EXHIBIT A AND B) LS 1.00 1.000.00$0.00$0.00
S-9NEW DESIGN GRADE LS 1.00 1.000.00$0.00$0.00
S-102025 TRAFFIC CONTROL AT SHELDON PIT WD 19.00 0.0019.00$3,054.00$58,026.00
S-11QUANTITY DISCREPANCY ADJUSTMENT 2025 LS 1.00 0.001.00$50,000.00$50,000.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 0.00 0.000.00$100.00 $0.00
LIQUIDATED DAMAGESDAY 0.00 0.000.00$2,000.00 $0.00
LABOR COMPLIANCEVIOLATION 0.00 0.000.00$250.00 $0.00
AFFIRMATIVE ACTIONVIOLATION 0.00 0.000.00$200.00 $0.00
BEST MANAGEMENT PRACTICEVIOLATION 0.00 0.000.00$1,000.00 $0.00
SCHEDULE UPDATEMONTHLY 0.00 0.000.00$250.00 $0.00
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 0.00 0.000.00$1.00 $0.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,903,330.44 $5,682,904.44 $220,426.00
Retained $295,166.52 $284,145.23 $11,021.29
Deducted $0.00 $0.00 $0.00
Due $5,608,163.92 $5,398,759.21 $209,404.71



*The term "As-Built" used by the Department of Public Works in combination with the Engineer's Monthly Estimate process indicates that the project has been field accepted and that the pay quantities and deductions as detailed above are FINAL. Unless a certified letter is received by this office within 14 calendar days disputing the amounts shown, an acceptance letter will be filed with the Board of Supervisors authorizing the release of retention.