| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.85
| 0.65 | 0.20 | $66,650.00 | $13,330.00 |
| 5 | OFFICE FACILITIES | 5.00 | MTH |
5.00
| 4.00 | 1.00 | $12,700.00 | $12,700.00 |
| 10 | UNCLASSIFIED EXCAVATION (CHANNEL) | 7,226.00 | CY |
5,206.00
| 5,031.00 | 175.00 | $27.00 | $4,725.00 |
| 15 | CRUSHED MISCELLANEOUS BASE | 111.00 | CY |
111.00
| 0.00 | 111.00 | $220.00 | $24,420.00 |
| 18 | STRUCTURE CONCRETE | 43.00 | CY |
43.00
| 0.00 | 43.00 | $2,400.00 | $103,200.00 |
| 19 | BAR REINFORCING STEEL (EPOXY-COATED) | 3,709.00 | LB |
3,709.00
| 0.00 | 3,709.00 | $9.00 | $33,381.00 |
| 33 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.65
| 0.50 | 0.15 | $12,420.00 | $1,863.00 |
| S-4 | CREATE KEYWAY IN LEVEE AND SUBSEQUENTLY REBUILD | | T&M |
6,005.89
| 0.00 | 6,005.89 | $1.00 | $6,005.89 |