| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
1.00
| 0.50 | 0.50 | $10,000.00 | $5,000.00 |
| 11 | IMPLEMENTATION OF THE DEBRIS CONTAINMENT AND CONTROL PLAN | 1.00 | LS |
1.00
| 0.75 | 0.25 | $30,000.00 | $7,500.00 |
| S-4 | REMOVE UNSOUND CONCRETE (CO #5) | | SF |
70.00
| 0.00 | 70.00 | $330.00 | $23,100.00 |
| S-5 | SPALL REPAIR BARRIER RAIL N/SIDE (CO #5) | | SF |
70.00
| 0.00 | 70.00 | $360.00 | $25,200.00 |
| S-6 | TRAFFIC CONTROL/MOBILIZATION (CO #6) | | LS |
0.50
| 0.00 | 0.50 | $20,000.00 | $10,000.00 |
| S-7 | CHANGEABLE MESSAGE SIGN (CO #6) | | LS |
0.50
| 0.00 | 0.50 | $5,000.00 | $2,500.00 |
| S-8 | CHANGEABLE MESSAGE SIGN (CO #6) | | LS |
0.50
| 0.00 | 0.50 | $15,000.00 | $7,500.00 |
| S-11 | STRUCTURE CONCRETE (CO #7) | | CY |
2.00
| 0.00 | 2.00 | $10,000.00 | $20,000.00 |