Los Angeles County Public Works
Project Management Division III
Progress Payment 7
Project Name: Bridge Preventive Maintenance Program - Group 16 Cities
Contractor: Beador Construction Company, Inc.
2900 Bristol Street, Suite D204
Costa Mesa, CA 92626-5981
Project ID: RDC0015922
Federal Number(s): BPMPL-5953(726)
Original Contract: $2,210,300.00
Awarded: 5/20/2024
Period Ending: 1/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 1.00 0.500.50$10,000.00$5,000.00
11IMPLEMENTATION OF THE DEBRIS CONTAINMENT AND CONTROL PLAN1.00LS 1.00 0.750.25$30,000.00$7,500.00
S-4REMOVE UNSOUND CONCRETE (CO #5) SF 70.00 0.0070.00$330.00$23,100.00
S-5SPALL REPAIR BARRIER RAIL N/SIDE (CO #5) SF 70.00 0.0070.00$360.00$25,200.00
S-6TRAFFIC CONTROL/MOBILIZATION (CO #6) LS 0.50 0.000.50$20,000.00$10,000.00
S-7CHANGEABLE MESSAGE SIGN (CO #6) LS 0.50 0.000.50$5,000.00$2,500.00
S-8CHANGEABLE MESSAGE SIGN (CO #6) LS 0.50 0.000.50$15,000.00$7,500.00
S-11STRUCTURE CONCRETE (CO #7) CY 2.00 0.002.00$10,000.00$20,000.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGETED WORKER HIRING PROGRAMVIOLATION 297.29 0.00297.29$1.00 $297.29

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,198,453.91 $2,097,653.91 $100,800.00
Retained $54,961.41 $52,441.69 $2,519.72
Deducted $30,671.72 $30,374.43 $297.29
Due $2,112,820.78 $2,014,837.79 $97,982.99