Project Name: Big Pines Hwy et al -Guardrail Replacement On-System (2020 Bobcat Fire)
Contractor: Access Pacific, Inc.
2835 Sierra Grande Street
Pasadena, CA 91107
Project ID: RDC0016498
Federal Number(s): ER-15A6(008)
Original Contract: $474,400.00
Awarded: 5/6/2025
Period Ending: 10/20/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)1.00MTH 0.00 0.000.00$500.00$0.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
4PREPARATION OF TWW WORKPLAN (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
5CLEARING AND GRUBBING1.00LS 1.00 1.000.00$1,000.00$0.00
6UNCLASSIFIED EXCAVATION58.00CY 58.00 58.000.00$80.00$0.00
7SHOULDER GRADING1,013.00LF 1,013.00 1,013.000.00$40.00$0.00
8REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS)638.00LF 638.00 638.000.00$50.00$0.00
9REMOVE AND SALVAGE EXISTING TEMPORARY BARRIER1.00LS 1.00 1.000.00$20,000.00$0.00
10TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE9,680.00LB 0.00 0.000.00$3.00$0.00
11MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK)489.00LF 501.00 489.0012.00$500.00$6,000.00
12IN-LINE TERMINAL SYSTEM (TYPE MSKT-SP-MGS)7.00EA 7.00 7.000.00$3,000.00$0.00
13END ANCHOR ASSEMBLY (TYPE SFT)1.00EA 1.00 1.000.00$3,000.00$0.00
14MIDWEST GUARDRAIL SYSTEM (END CAP, TYPE B)1.00EA 1.00 1.000.00$3,000.00$0.00
15TYPE E DELINEATOR (FLEXIBLE POST) CALTRANS STD PLAN A73C33.00EA 36.00 33.003.00$100.00$300.00
16TRAFFIC CONTROL1.00LS 1.00 1.000.00$50,000.00$0.00
17CHANGEABLE MESSAGE SIGN4.00EA 6.00 6.000.00$4,000.00$0.00
S-1REVISED NTP2 DATE WD 0.00 0.000.00$0.00$0.00
S-2UNFORESEEN BOULDER WORK LS 1.00 1.000.00$26,500.00$0.00
S-3TREATED WOOD WASTE (TRANSPORTATION & DISPOSAL) LB 5,540.00 5,540.000.00$3.50$0.00
S-4TIME EXTENSION (PUNCHLIST WORK) WD 2.00 2.000.00$0.00$0.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 0.00 0.000.00$100.00 $0.00
LIQUIDATED DAMAGESDAY 0.00 0.000.00$2,000.00 $0.00
LABOR COMPLIANCEVIOLATION 0.00 0.000.00$250.00 $0.00
AFFIRMATIVE ACTIONVIOLATION 0.00 0.000.00$200.00 $0.00
BEST MANAGEMENT PRACTICEVIOLATION 0.00 0.000.00$1,000.00 $0.00
SCHEDULE UPDATEMONTHLY 0.00 0.000.00$250.00 $0.00
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 0.00 0.000.00$1.00 $0.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $505,050.00 $497,750.00 $7,300.00
Retained $25,252.50 $24,887.50 $365.00
Deducted $0.00 $0.00 $0.00
Due $479,797.50 $472,862.50 $6,935.00



*The term "As-Built" used by the Department of Public Works in combination with the Engineer's Monthly Estimate process indicates that the project has been field accepted and that the pay quantities and deductions as detailed above are FINAL. Unless a certified letter is received by this office within 14 calendar days disputing the amounts shown, an acceptance letter will be filed with the Board of Supervisors authorizing the release of retention.