| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 9.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.20
| 0.10 | 0.10 | $8,000.00 | $800.00 |
| 8 | IMPLEMENTATION OF THE NOISE MITIGATION PLAN | 1.00 | LS |
0.20
| 0.10 | 0.10 | $16,500.00 | $1,650.00 |
| 9 | TEMPORARY SOUND WALLS | 1.00 | LS |
0.50
| 0.25 | 0.25 | $93,500.00 | $23,375.00 |
| 10 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.20
| 0.10 | 0.10 | $35,000.00 | $3,500.00 |
| 13 | IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN | 1.00 | LS |
1.00
| 0.00 | 1.00 | $8,965.00 | $8,965.00 |
| 14 | REMOVAL AND DISPOSAL OF NON-HAZARDOUS ASBESTOS WASTE | 1.00 | LS |
1.00
| 0.00 | 1.00 | $19,860.00 | $19,860.00 |
| 15 | OFFICE FACILITIES | 10.00 | MTH |
2.00
| 1.00 | 1.00 | $3,000.00 | $3,000.00 |
| 16 | MOBILIZATION | 1.00 | LS |
0.5514
| 0.00 | 0.5514 | $624,020.00 | $344,084.63 |
| 17 | BARRICADE POSTS, STD PLAN W-14 | 4.00 | EA |
2.00
| 0.00 | 2.00 | $1,250.00 | $2,500.00 |
| 18 | VIDEO CAMERA SURVEY | 1.00 | EA |
1.00
| 0.00 | 1.00 | $2,750.00 | $2,750.00 |
| 23 | CONDUCTOR BOREHOLE | 100.00 | LF |
100.00
| 0.00 | 100.00 | $165.00 | $16,500.00 |
| 24 | CONDUCTOR CASING | 103.00 | LF |
103.00
| 0.00 | 103.00 | $550.00 | $56,650.00 |
| 25 | PILOT BOREHOLE | 500.00 | LF |
500.00
| 0.00 | 500.00 | $110.00 | $55,000.00 |
| 26 | GEOPHYSICAL BOREHOLE LOGS | 1.00 | EA |
1.00
| 0.00 | 1.00 | $6,050.00 | $6,050.00 |
| 32 | 6" CRUSHED ROCK | 3.00 | CY |
3.00
| 0.00 | 3.00 | $750.00 | $2,250.00 |
| 34 | SEEPAGE PIT | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,900.00 | $5,900.00 |
| 40 | REINFORCED CONCRETE WINGWALL AND HEADWALL | 1.00 | LS |
1.00
| 0.00 | 1.00 | $21,000.00 | $21,000.00 |
| 43 | MASONRY BLOCK WALL | 804.00 | LF |
603.00
| 41.00 | 562.00 | $303.00 | $170,286.00 |
| 45 | 12" HDPE PIPE | 15.00 | LF |
8.00
| 0.00 | 8.00 | $85.00 | $680.00 |
| 56 | UNCLASSIFIED EXCAVATION (RETENTION BASIN) | 226.00 | CY |
226.00
| 208.00 | 18.00 | $110.00 | $1,980.00 |
| 67 | CONCRETE CATCH BASIN PER SPPWC STD PLAN 305-3 & MISC. CONCRETE | 1.00 | LS |
1.00
| 0.00 | 1.00 | $10,600.00 | $10,600.00 |
| 69 | INITIAL VIDEO INSPECTION | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,500.00 | $1,500.00 |
| 74 | CONCRETE CURB PER SPPWC STD PLAN 120-2, A3-6 | 184.00 | LF |
160.00
| 0.00 | 160.00 | $50.00 | $8,000.00 |
| 76 | TEMPORARY POWER (WELL 4-91) | 6.00 | MTH |
1.20
| 0.60 | 0.60 | $21,560.00 | $12,936.00 |
|