| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 0.80 | 0.20 | $30,000.00 | $6,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 0.95 | 0.05 | $30,000.00 | $1,500.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
1.00
| 0.95 | 0.05 | $5,000.00 | $250.00 |
| 15 | COMMUNITY RELATIONS (ALLOWANCE OF $50,000) | 50,000.00 | AL |
6,500.00
| 0.00 | 6,500.00 | $1.00 | $6,500.00 |
| 16 | OFFICE FACILITIES | 8.00 | MTH |
8.00
| 7.00 | 1.00 | $25,000.00 | $25,000.00 |
| 22 | WATER SERVICE, 1.0", STD PLAN W-7 | 11.00 | EA |
11.00
| 10.00 | 1.00 | $6,000.00 | $6,000.00 |
| 24 | RECONNECT EXISTING WATER SERVICE | 6.00 | EA |
7.00
| 6.00 | 1.00 | $7,000.00 | $7,000.00 |
| 25 | RECONNECT EXISTING WATER SERVICE WITH NEW METER BOX AND LID | 17.00 | EA |
17.00
| 16.00 | 1.00 | $8,000.00 | $8,000.00 |
| 26 | AIR RELEASE AND VACUUM VALVE ASSEMBLY, 2" | 2.00 | EA |
2.00
| 1.40 | 0.60 | $10,000.00 | $6,000.00 |
| 32 | FIRE HYDRANT, STD PLAN W-10 | 8.00 | EA |
8.00
| 7.00 | 1.00 | $20,000.00 | $20,000.00 |
| 36 | TRENCH BACKFILL SLURRY (CLASS 140-S-100) | 26.00 | CY |
86.00
| 76.00 | 10.00 | $500.00 | $5,000.00 |
| 38 | RECONNECT EXISTING SAMPLING STATION | 1.00 | EA |
1.00
| 0.75 | 0.25 | $5,000.00 | $1,250.00 |
| 39 | CATHODIC PROTECTION ANODE AND TEST STATION, STD PLAN W-39 | 1.00 | EA |
1.00
| 0.90 | 0.10 | $15,000.00 | $1,500.00 |
| 42 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.95 | 0.05 | $100,000.00 | $5,000.00 |
| S-16 | ADDITIONAL PAVING | | TONS |
71.00
| 30.00 | 41.00 | $575.00 | $23,575.00 |