Los Angeles County Public Works
Project Management Division III
Progress Payment 15
Project Name: West Whittier Los Nietos Mines Boulevard et al
Contractor: Excel Paving Company
2230 Lemon Avenue
Long Beach, CA 90806-5195
Project ID: RMD4403002
Federal Number(s): None
Original Contract: $8,974,979.80
Awarded: 7/15/2024
Period Ending: 1/20/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
14TREE REMOVAL (6"-12" DIAMETER)1.00EA 3.00 1.002.00$700.00$1,400.00
51INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT110.00LF 4,468.00 0.004,468.00$16.00$71,488.00
88DETAIL 22 (THERMOPLASTIC)8,984.00LF 8,329.00 0.008,329.00$2.00$16,658.00
89DETAIL 25 (THERMOPLASTIC)541.00LF 520.00 0.00520.00$1.00$520.00
90DETAIL 29 (THERMOPLASTIC)1,181.00LF 541.00 0.00541.00$2.00$1,082.00
91DETAIL 32 (THERMOPLASTIC)8,127.00LF 3,576.00 0.003,576.00$2.00$7,152.00
92DETAIL 38 (THERMOPLASTIC)1,758.00LF 1,758.00 0.001,758.00$2.00$3,516.00
93DETAIL 39 (THERMOPLASTIC)7,728.00LF 7,728.00 0.007,728.00$1.00$7,728.00
94DETAIL 40 (THERMOPLASTIC)208.00LF 208.00 0.00208.00$1.00$208.00
95DETAIL 9 (THERMOPLASTIC)12,030.00LF 12,030.00 0.0012,030.00$1.00$12,030.00
96DETAIL 38A (THERMOPLASTIC)770.00LF 742.00 0.00742.00$2.00$1,484.00
97DETAIL 39A (THERMOPLASTIC)10,340.00LF 9,650.00 0.009,650.00$1.00$9,650.00
98DETAIL 27B (THERMOPLASTIC)6,781.00LF 6,826.00 0.006,826.00$1.00$6,826.00
99DETAIL 37B (THERMOPLASTIC)1,076.00LF 802.00 0.00802.00$2.00$1,604.00
100PAVEMENT MARKINGS (THERMOPLASTIC)26,125.00SF 17,488.00 0.0017,488.00$4.00$69,952.00
10112" STRIPING (THERMOPLASTIC)1,133.00LF 1,097.00 0.001,097.00$3.00$3,291.00
1028" STRIPING (THERMOPLASTIC)3,093.00LF 2,978.00 0.002,978.00$3.00$8,934.00
103CURB MARKINGS (ONE-COAT PAINT)854.00LF 884.00 0.00884.00$2.00$1,768.00
104REMOVE STRIPING AND MARKINGS (THERMOPLASTIC)705.00SF 705.00 0.00705.00$5.00$3,525.00
105INSTALL FIRE HYDRANT LOCATION RPM40.00EA 20.00 0.0020.00$15.00$300.00
127GREEN COLORED PAVEMENT MARKING9,684.00SF 2,952.00 0.002,952.00$9.00$26,568.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $9,932,678.45 $9,676,994.45 $255,684.00
Retained $496,633.92 $483,849.72 $12,784.20
Deducted $0.00 $0.00 $0.00
Due $9,436,044.53 $9,193,144.73 $242,899.80



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.