| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
5.00
| 4.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.31
| 0.26 | 0.05 | $324,000.00 | $16,200.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
5.00
| 4.00 | 1.00 | $4,000.00 | $4,000.00 |
| 10 | MAINTENANCE AND REMOVAL OF TEMPORARY SOUND BARRIER | 1,000.00 | LF |
51.00
| 34.00 | 17.00 | $30.00 | $510.00 |
| 15 | INSTALLATION OF WILDLIFE EXCLUSIONARY FENCING | 3,500.00 | LF |
1,960.00
| 1,645.00 | 315.00 | $20.00 | $6,300.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
82.00
| 68.00 | 14.00 | $1,800.00 | $25,200.00 |
| 23 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.31
| 0.23 | 0.08 | $34,000.00 | $2,720.00 |
| 26 | MOBILIZATION | 1.00 | LS |
0.73
| 0.49 | 0.24 | $2,100,000.00 | $504,000.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
5.00
| 4.00 | 1.00 | $5,000.00 | $5,000.00 |
| 38 | PERMEABLE ZONE MATERIAL | 2,691.00 | CY |
920.00
| 885.00 | 35.00 | $80.00 | $2,800.00 |
| 74 | SPILLWAY WALL BUTTRESS COMPLETE IN PLACE | 1.00 | LS |
0.23
| 0.20 | 0.03 | $6,000,000.00 | $180,000.00 |
| 80 | CONTROL BUILDING | 1.00 | LS |
0.20
| 0.04 | 0.16 | $700,000.00 | $112,000.00 |